Anantam - Phase I

by Oyster Living LLP · Bhiwandi, Thane

Possession date of Anantam - Phase I: 31 August 2024, moved from 30 June 2022 (26 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51700017123. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (August 2024) has passed.

What do you want to know about Anantam - Phase I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Anantam - Phase I has moved

  1. 30 June 2022

    Completion date given when the project was registered

  2. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51700011397)

    Reason the builder gave MahaRERA:
    “Dear Authority, This is with reference to our Ongoing Project Named: Anantam ¬ Phase I situated at 13/2 at Pimpalas, Bhiwandi, Thane, 421302. With MAHARERA Registration No. P51700017123. We request you to grant the extension to the above-me…” Read the full reason“Dear Authority, This is with reference to our Ongoing Project Named: Anantam ¬ Phase I situated at 13/2 at Pimpalas, Bhiwandi, Thane, 421302. With MAHARERA Registration No. P51700017123. We request you to grant the extension to the above-mentioned project from 30th June 2022 to 30th June 2023. Herewith this letter we inform you that Because of the hardship of plot is causing hardship in the construction activities & agencies are not been able to work simultaneously thus we need more time to complete the project, As a result, we foresee delay in the project. Hence, we request you to grant th…”
  3. 31 August 2024

    Extended at the builder's request (MahaRERA application EXT51700017265)

    Reason the builder gave MahaRERA:
    “Respected Authority, This is with reference to our Ongoing Project Named: Anantam Phase I situated at Plot bearing /CTS/ Survey / Final Plot No. : 13/2 at Pimpalas, Bhiwandi, Thane, 421302 with MAHARERA Registration No. P51700017123. We req…” Read the full reason“Respected Authority, This is with reference to our Ongoing Project Named: Anantam Phase I situated at Plot bearing /CTS/ Survey / Final Plot No. : 13/2 at Pimpalas, Bhiwandi, Thane, 421302 with MAHARERA Registration No. P51700017123. We request you to grant the extension to the above-mentioned project from 30th June 2023 to 31st Aug 2024. Herewith this letter we inform you that Because of the hardship of plot. we need more time to complete the project, as plot size is very small & is causing hardship in the construction activities & agencies are not been able to work simultaneously. As a re…”

Source: Anantam - Phase I’s extension records on MahaRERA (P51700017123), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Anantam - Phase I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the August 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51700017123
Status
Lapsed (registration period ended)
Builder
Oyster Living LLP
Location
Bhiwandi, Thane · 421302
Project type
Others
Registered on
16 Jul 2018
Completion date at registration
June 2022
Latest completion date
August 2024
Delay so far
26 months
Homes
96
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Anantam - Phase I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B and C Wing100%12%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anantam - Phase I every month.

Anantam - Phase I: buildings, flats and land, as filed on MahaRERA

  • Buildings: B and C Wing (9 floors)
  • Land: 2,380 sq m (about 0.6 acres) · sanctioned built-up 11,497 sq m

The builder’s record and reviews

Oyster Living has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 1 still being built, none past the promised date yet; 2 lapsed. 48 complaints on MahaRERA across 2 projects.

Read Google reviews of Anantam - Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Anantam - Phase I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Anantam - Phase I

What is the possession date of Anantam - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Anantam - Phase I in Bhiwandi, Thane is 31 August 2024 — 26 months later than 30 June 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Anantam - Phase I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Anantam - Phase I's builder has filed on MahaRERA, the official one, is 31 August 2024, already 26 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Anantam - Phase I extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Anantam - Phase I's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2023, giving the reason "Dear Authority, This is with reference to our Ongoing Project Named: Anantam ¬ Phase I situated at 13/2 at Pimpalas, Bhiwandi, Thane, 421302. With MAHARERA Registration No. P51700017123. We request you to grant the extension to the above-mentioned project from 30th June 2022 to 30th June 2023. Herewith this letter we inform you that Because of the hardship of plot is causing hardship in the construction activities & agencies are not been able to work simultaneously thus we need more time to complete the project, As a result, we foresee delay in the project. Hence, we request you to grant th…"; to 31 August 2024, giving the reason "Respected Authority, This is with reference to our Ongoing Project Named: Anantam Phase I situated at Plot bearing /CTS/ Survey / Final Plot No. : 13/2 at Pimpalas, Bhiwandi, Thane, 421302 with MAHARERA Registration No. P51700017123. We request you to grant the extension to the above-mentioned project from 30th June 2023 to 31st Aug 2024. Herewith this letter we inform you that Because of the hardship of plot. we need more time to complete the project, as plot size is very small & is causing hardship in the construction activities & agencies are not been able to work simultaneously. As a re…".

What is the RERA number of Anantam - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Anantam - Phase I in Bhiwandi, Thane is P51700017123.

Is Anantam - Phase I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Anantam - Phase I is registered as P51700017123 and its status is "Lapsed (registration period ended)".

What is the construction status of Anantam - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Anantam - Phase I's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on B and C Wing is 12% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Anantam - Phase I have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Anantam - Phase I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Anantam - Phase I is registered on MahaRERA as P51700017123, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 26 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Anantam - Phase I have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Anantam - Phase II (P51700017195, possession 30 Jun 2023). Check that your agreement names the registration of your own wing.

How can I get updates if Anantam - Phase I's possession date changes?

The latest dates are on Anantam - Phase I's MahaRERA page (P51700017123). GharKundli's Kundli Watch sends a free WhatsApp update on Anantam - Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Anantam - Phase I have?

According to GharKundli's check of MahaRERA records (updated November 2026), Anantam - Phase I has one building filed: B and C Wing with 9 floors.

How big is the land of Anantam - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Anantam - Phase I stands on 2,380 sq m of land (about 0.6 acres), with 11,497 sq m of sanctioned built-up area.

What is the track record of Anantam - Phase I's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Oyster Living has 3 projects on MahaRERA since 2018, this one included. Of the 3 GharKundli has checked: 1 still being built, none past the promised date yet; 2 lapsed. 48 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Anantam - Phase I?

Google Maps has reviews of Anantam - Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Anantam - Phase I?

Anantam - Phase I by Oyster Living LLP is in Bhiwandi, Thane (pincode 421302), Maharashtra, and is registered on MahaRERA as P51700017123, per GharKundli's check of MahaRERA records.

How many homes are in Anantam - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Anantam - Phase I has 96 homes in 1 tower registered on MahaRERA.

When was Anantam - Phase I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Anantam - Phase I was registered on MahaRERA on 16 July 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on Anantam - Phase I?

No court cases are listed for Anantam - Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Anantam - Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Oyster Living LLP, which has 2 other projects registered on MahaRERA.

Other projects in Bhiwandi

All 382 projects in Bhiwandi (421302) →

Other projects by Oyster Living LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.