Possession date of SHRI GAJANAN: 31 December 2026, moved from 31 December 2019 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800009842, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SHRI GAJANAN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHRI GAJANAN has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 31 December 2020

    Extended at the builder's request (MahaRERA application EXT52800005309)

    Reason the builder gave MahaRERA: “Payment Recovery.”
  3. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT52800009847)

    Reason the builder gave MahaRERA: “Due to Covid 19 lockdown work was stopped, labour unavailability, poor market conditions, delay of payments from customers.”
  4. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52800013082)

    Reason the builder gave MahaRERA: “Due to project plan revised with number 518/2817 dated 07/09/2021, economic slowdown, poor market conditions, labour unavailability and delay in payments from customers.”
  5. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52800018683)

    Reason the builder gave MahaRERA:
    “Due to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability and delay in…” Read the full reason“Due to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability and delay in payments from customers.”
  6. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT52800026019)

    Reason the builder gave MahaRERA:
    “Due to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability and delay in…” Read the full reason“Due to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability and delay in payments from customers.”
  7. 31 December 2026

    Extended at the builder's request (MahaRERA application EA01042620524)

    Reason the builder gave MahaRERA:
    “Due to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability, and delay i…” Read the full reason“Due to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability, and delay in payments from customers.”

Source: SHRI GAJANAN’s extension records on MahaRERA (P52800009842), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHRI GAJANAN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800009842
Status
Registered and active
Builder
UTSAHI LILADHAR CHAVANDE
Location
Ratnagiri · 415612
Project type
Others
Registered on
22 Aug 2017
Completion date at registration
December 2019
Latest completion date
December 2026
Delay so far
84 months
Homes
9
Sold or booked
47%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of SHRI GAJANAN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SHRI GAJANAN100%100%75%90%

Commencement certificate (CC), as filed on MahaRERA

  • SHRI GAJANAN: covers 0 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHRI GAJANAN every month.

SHRI GAJANAN: buildings, flats and land, as filed on MahaRERA

  • Buildings: SHRI GAJANAN (6 floors, 18 units)
  • Land: 261 sq m (about 0.1 acres) · sanctioned built-up 388 sq m · recreational space 133 sq m
  • Boundaries filed include: ZARNI ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SHRI GAJANAN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHRI GAJANAN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHRI GAJANAN

What is the possession date of SHRI GAJANAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SHRI GAJANAN in Ratnagiri is 31 December 2026 — 84 months later than 31 December 2019, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SHRI GAJANAN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHRI GAJANAN's builder has filed on MahaRERA, the official one, is 31 December 2026, already 84 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHRI GAJANAN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GAJANAN's builder applied to MahaRERA to extend the completion date 6 times: to 31 December 2020, giving the reason "Payment Recovery."; to 31 December 2022, giving the reason "Due to Covid 19 lockdown work was stopped, labour unavailability, poor market conditions, delay of payments from customers."; to 31 December 2023, giving the reason "Due to project plan revised with number 518/2817 dated 07/09/2021, economic slowdown, poor market conditions, labour unavailability and delay in payments from customers."; to 31 December 2024, giving the reason "Due to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability and delay in payments from customers."; to 31 December 2025, giving the reason "Due to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability and delay in payments from customers."; to 31 December 2026, giving the reason "Due to approved additional building construction for second and third floor on existing approved ground and first floor for residential use with permission no. 518/2817 dated 07/09/2021, market conditions, labour unavailability, and delay in payments from customers.".

What is the RERA number of SHRI GAJANAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SHRI GAJANAN in Ratnagiri is P52800009842.

Is SHRI GAJANAN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GAJANAN is registered as P52800009842 and its status is "Registered and active".

What is the construction status of SHRI GAJANAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GAJANAN's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SHRI GAJANAN is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.

Does SHRI GAJANAN have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SHRI GAJANAN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GAJANAN is registered on MahaRERA as P52800009842, its completion date has moved 84 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHRI GAJANAN's possession date changes?

The latest dates are on SHRI GAJANAN's MahaRERA page (P52800009842). GharKundli's Kundli Watch sends a free WhatsApp update on SHRI GAJANAN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHRI GAJANAN have?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GAJANAN has one building filed: SHRI GAJANAN with 6 floors and 18 units.

How big is the land of SHRI GAJANAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GAJANAN stands on 261 sq m of land (about 0.1 acres), with 388 sq m of sanctioned built-up area and 133 sq m of recreational open space.

Where can I read reviews of SHRI GAJANAN?

Google Maps has reviews of SHRI GAJANAN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHRI GAJANAN?

SHRI GAJANAN by UTSAHI LILADHAR CHAVANDE is in Ratnagiri (pincode 415612), Maharashtra, and is registered on MahaRERA as P52800009842, per GharKundli's check of MahaRERA records. Its boundaries filed there include ZARNI ROAD.

How many homes are in SHRI GAJANAN?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GAJANAN has 9 homes in 1 tower registered on MahaRERA, and 47% of them are sold or booked.

When was SHRI GAJANAN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SHRI GAJANAN was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHRI GAJANAN?

No court cases are listed for SHRI GAJANAN on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SHRI GAJANAN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is UTSAHI LILADHAR CHAVANDE.

All projects with possession due in 2026 in Ratnagiri →

Other projects in pincode 415612

All 63 projects in Ratnagiri (415612) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.