KHAN RESIDENCY
by MMM BUILDCON · Ratnagiri
Possession date of KHAN RESIDENCY: 30 January 2027, moved from 31 December 2025 (9 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52800079742, and currently active. Its completion date has moved from December 2025 to January 2027: 9 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about KHAN RESIDENCY?
How the possession date of KHAN RESIDENCY has moved
31 December 2025
Completion date given when the project was registered
30 September 2026
Extended at the builder's request (MahaRERA application EA05012619284)
Reason the builder gave MahaRERA: “Almost project is completed only 30% is left for completion.”
30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: KHAN RESIDENCY’s extension records on MahaRERA (P52800079742), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KHAN RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52800079742
- Status
- Registered and active
- Builder
- MMM BUILDCON
- Location
- Ratnagiri · 415612
- Project type
- Others
- Registered on
- 24 Mar 2025
- Completion date at registration
- December 2025
- Latest completion date
- January 2027
- Delay so far
- 9 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 15
- Sold or booked
- 50%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of KHAN RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KHAN RESIDENCY | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- KHAN RESIDENCY: covers 8 floors
Latest CC order on MahaRERA: dated 25/03/2026.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KHAN RESIDENCY every month.
KHAN RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: KHAN RESIDENCY (8 floors, 26 units)
- Car parking: 9 covered
- Land: 600 sq m (about 0.1 acres) · sanctioned built-up 1,692 sq m
- Boundaries filed include: 18-28 Mts Wide Mazgaon Road
The builder’s record and reviews
M M M Buildcon has 3 projects on MahaRERA since 2025, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA.
Read Google reviews of KHAN RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KHAN RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KHAN RESIDENCY
What is the possession date of KHAN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KHAN RESIDENCY in Ratnagiri is 30 January 2027 — 9 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for KHAN RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KHAN RESIDENCY's builder has filed on MahaRERA, the official one, is 30 January 2027, already 9 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KHAN RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated October 2026), KHAN RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 30 September 2026, giving the reason "Almost project is completed only 30% is left for completion.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of KHAN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KHAN RESIDENCY in Ratnagiri is P52800079742.
Is KHAN RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KHAN RESIDENCY is registered as P52800079742 and its status is "Registered and active".
What is the construction status of KHAN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), KHAN RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on KHAN RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does KHAN RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is KHAN RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), KHAN RESIDENCY is registered on MahaRERA as P52800079742, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KHAN RESIDENCY's possession date changes?
The latest dates are on KHAN RESIDENCY's MahaRERA page (P52800079742). GharKundli's Kundli Watch sends a free WhatsApp update on KHAN RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KHAN RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), KHAN RESIDENCY has one building filed: KHAN RESIDENCY with 8 floors and 26 units.
How much parking does KHAN RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 9 covered car parking spaces for KHAN RESIDENCY.
How big is the land of KHAN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), KHAN RESIDENCY stands on 600 sq m of land (about 0.1 acres), with 1,692 sq m of sanctioned built-up area.
What is the track record of KHAN RESIDENCY's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), M M M Buildcon has 3 projects on MahaRERA since 2025, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 6 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of KHAN RESIDENCY?
Google Maps has reviews of KHAN RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KHAN RESIDENCY?
KHAN RESIDENCY by MMM BUILDCON is in Ratnagiri (pincode 415612), Maharashtra, and is registered on MahaRERA as P52800079742, per GharKundli's check of MahaRERA records. Its boundaries filed there include 18-28 Mts Wide Mazgaon Road.
How many homes are in KHAN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), KHAN RESIDENCY has 15 homes in 1 tower registered on MahaRERA, and 50% of them are sold or booked.
When was KHAN RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KHAN RESIDENCY was registered on MahaRERA on 24 March 2025. GharKundli did not find a title report on the land on file there.
Are there court cases on KHAN RESIDENCY?
No court cases are listed for KHAN RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of KHAN RESIDENCY?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MMM BUILDCON, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of KHAN RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Ratnagiri →
Other projects in pincode 415612
- SHRI GAJANAN
- LAXMI KEHSAV NAGAR PHASE II
- Searock Residency
- KOHINOOR ELITE
- KOHINOOR CHAITANYA
- K.S.P. DHANALAXMI
- ASHTVINAYAK GAURAV SANKUL
- RAM VIJAY
Other projects by MMM BUILDCON
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.