Landmark Sai Narayana Residency
by MM Landmark Realty LLP · Bhiwandi Thane, Thane 421302Registered on MahaRERA as “Sai Narayana Residency”
What’s in the report? →Possession date of Landmark Sai Narayana Residency (MahaRERA P51700034963): 30 April 2027, moved from 31 December 2025 (12 months later). It has 114 homes, 92% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700034963, and currently active. Its completion date has moved from December 2025 to April 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700034963, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Landmark Sai Narayana Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Landmark Sai Narayana Residency has moved
31 December 2025
Completion date given when the project was registered
30 December 2026
Extended at the builder's request (MahaRERA application EA17112518343)
Reason the builder gave MahaRERA:
“a) While excavation and lowering of water level we were supposed to take care since the project land is already surrounded by residential buildings and therefore this activity went slowly and took time. b) The area is which project is to be…” Read the full reason
“a) While excavation and lowering of water level we were supposed to take care since the project land is already surrounded by residential buildings and therefore this activity went slowly and took time. b) The area is which project is to be constructed and completed is entirely a residential area, therefore there are limitations in time of construction work on daily basis. c) Apart from rainy season, unseasonal rainfall in the year 2024 led to hurdle in speed of construction work. d) There was shortage of labour, therefore regular flow of work got hampered. e) On account of aforesaid factor…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Landmark Sai Narayana Residency’s extension records on MahaRERA (P51700034963), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Landmark Sai Narayana Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700034963
- Status
- Registered and active
- Builder
- MM Landmark Realty LLP
- Location
- Bhiwandi Thane, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 28 Apr 2022
- Completion date at registration
- December 2025
- Latest completion date
- April 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 114
- Sold or booked
- 92%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Landmark Sai Narayana Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Sai Narayan Residency Wing A | 100% | 100% | 100% | 85% |
| Sai Narayana Residency Wing B | 100% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Sai Narayan Residency Wing A: covers 19 floors
- Sai Narayana Residency Wing B: covers 2 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Landmark Sai Narayana Residency every 1–2 months.
Landmark Sai Narayana Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: Sai Narayan Residency Wing A (20 floors, 105 units) · Sai Narayana Residency Wing B (3 floors, 9 units)
- Car parking: 50 covered
- Land: 4,050 sq m (about 1.0 acres) · sanctioned built-up 7,558 sq m
- Boundaries filed include: Sai Complex
- Land, as filed: S.No.14, H.No. 4 Of Village Kalher, Tal-Bhiwandi, Dist-Thane
- Map: Get directions
The builder’s record and reviews
MM Landmark Realty has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 14 months late). No complaints on MahaRERA.
Read Google reviews of Landmark Sai Narayana Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Landmark Sai Narayana Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Landmark Sai Narayana Residency
What is the possession date of Landmark Sai Narayana Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Landmark Sai Narayana Residency in Bhiwandi Thane, Thane is 30 April 2027 — 12 months later than 31 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Landmark Sai Narayana Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Landmark Sai Narayana Residency's builder has filed on MahaRERA, the official one, is 30 April 2027, already 12 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Landmark Sai Narayana Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Landmark Sai Narayana Residency's builder applied to MahaRERA to extend the completion date once: to 30 December 2026, giving the reason "a) While excavation and lowering of water level we were supposed to take care since the project land is already surrounded by residential buildings and therefore this activity went slowly and took time. b) The area is which project is to be constructed and completed is entirely a residential area, therefore there are limitations in time of construction work on daily basis. c) Apart from rainy season, unseasonal rainfall in the year 2024 led to hurdle in speed of construction work. d) There was shortage of labour, therefore regular flow of work got hampered. e) On account of aforesaid factor…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Landmark Sai Narayana Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Landmark Sai Narayana Residency in Bhiwandi Thane, Thane is P51700034963.
Is Landmark Sai Narayana Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Landmark Sai Narayana Residency is registered as P51700034963 and its status is "Registered and active".
What is the current construction status of Landmark Sai Narayana Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Landmark Sai Narayana Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Landmark Sai Narayana Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Landmark Sai Narayana Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Landmark Sai Narayana Residency is registered on MahaRERA as P51700034963, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Landmark Sai Narayana Residency?
Landmark Sai Narayana Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Landmark Sai Narayana Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Landmark Sai Narayana Residency: gharkundli.com/tools/property-cost-calculator
Has Landmark Sai Narayana Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Landmark Sai Narayana Residency is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Landmark Sai Narayana Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Landmark Sai Narayana Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Landmark Sai Narayana Residency's possession date changes?
The latest dates are on Landmark Sai Narayana Residency's MahaRERA page (P51700034963). GharKundli's Kundli Watch sends a free WhatsApp update on Landmark Sai Narayana Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Landmark Sai Narayana Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Landmark Sai Narayana Residency has 2 buildings filed: Sai Narayan Residency Wing A with 20 floors and 105 units; Sai Narayana Residency Wing B with 3 floors and 9 units.
How much parking does Landmark Sai Narayana Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 50 covered car parking spaces for Landmark Sai Narayana Residency.
How big is the land of Landmark Sai Narayana Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Landmark Sai Narayana Residency stands on 4,050 sq m of land (about 1.0 acres), with 7,558 sq m of sanctioned built-up area.
What is the track record of Landmark Sai Narayana Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), MM Landmark Realty has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 14 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Landmark Sai Narayana Residency?
Google Maps has reviews of Landmark Sai Narayana Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Landmark Sai Narayana Residency?
Landmark Sai Narayana Residency by MM Landmark Realty LLP is in Bhiwandi Thane, Thane, pincode 421302, Maharashtra, and is registered on MahaRERA as P51700034963, per GharKundli's check of MahaRERA records. Its boundaries filed there include Sai Complex. Its land is filed as S.No.14, H.No. 4 Of Village Kalher, Tal-Bhiwandi, Dist-Thane. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).
How many flats are in Landmark Sai Narayana Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Landmark Sai Narayana Residency has 114 homes in 2 towers registered on MahaRERA, and 92% of them are sold or booked.
When was Landmark Sai Narayana Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Landmark Sai Narayana Residency was registered on MahaRERA on 28 April 2022. GharKundli did not find a title report on the land on file there.
Does Landmark Sai Narayana Residency have any legal issues or court cases?
No court cases are listed for Landmark Sai Narayana Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Landmark Sai Narayana Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MM Landmark Realty LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Landmark Sai Narayana Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Bhiwandi
- Ashoka Complex
- Kohinoor Uptown T1 & T6
- Sai Deep Residency
- Neelkanth Sadan
- Regal Square PH 4 Tower 6 and 8
- The Pallazo
- Arihant City Phase-ii - K Building
- Royal Park
Other projects by MM Landmark Realty LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.