Vastunirman Vrundavan Park
by SHREE VASTUNIRMAN DEVELOPERS · Devrung, Thane 421302Registered on MahaRERA as “VRUNDAVAN PARK”
What’s in the report? →Possession date of Vastunirman Vrundavan Park (MahaRERA P51700049309): 30 April 2028, moved from 31 March 2025 (33 months later). It has 70 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700049309, and currently active. Its completion date has moved from March 2025 to April 2028: 33 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700049309, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Vastunirman Vrundavan Park?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Vastunirman Vrundavan Park has moved
31 March 2025
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EXT51700027181)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, and temporary financial constraints.…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-12-2027…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Vastunirman Vrundavan Park’s extension records on MahaRERA (P51700049309), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vastunirman Vrundavan Park
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700049309
- Status
- Registered and active
- Builder
- SHREE VASTUNIRMAN DEVELOPERS
- Location
- Devrung, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 7 Feb 2023
- Completion date at registration
- March 2025
- Latest completion date
- April 2028
- Delay so far
- 33 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 70
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Vastunirman Vrundavan Park, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| JAI - BLDG NO 1 WING A WING B | 100% | 100% | 90% | 0% |
| JUI - BLDG NO 2 WING A WING B WING C | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vastunirman Vrundavan Park every 1–2 months.
Vastunirman Vrundavan Park: buildings, flats and land, as filed on MahaRERA
- Buildings: JAI - BLDG NO 1 WING A WING B (8 floors) · JUI - BLDG NO 2 WING A WING B WING C (8 floors)
- Land: 3,000 sq m (about 0.7 acres) · sanctioned built-up 6,442 sq m
- Land, as filed: 94/19, 94/23, 94/25
- Map: Get directions
The builder’s record and reviews
Shree Vastunirman Developers has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 15 months late). No complaints on MahaRERA.
Read Google reviews of Vastunirman Vrundavan Park →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vastunirman Vrundavan Park: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Vastunirman Vrundavan Park
What is the possession date of Vastunirman Vrundavan Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vastunirman Vrundavan Park in Devrung, Thane is 30 April 2028 — 33 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 33 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Vastunirman Vrundavan Park?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vastunirman Vrundavan Park's builder has filed on MahaRERA, the official one, is 30 April 2028, already 33 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vastunirman Vrundavan Park extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunirman Vrundavan Park's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-12-2027…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Vastunirman Vrundavan Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vastunirman Vrundavan Park in Devrung, Thane is P51700049309.
Is Vastunirman Vrundavan Park registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunirman Vrundavan Park is registered as P51700049309 and its status is "Registered and active".
What is the current construction status of Vastunirman Vrundavan Park? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunirman Vrundavan Park's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Vastunirman Vrundavan Park have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Vastunirman Vrundavan Park safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunirman Vrundavan Park is registered on MahaRERA as P51700049309, its completion date has moved 33 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Vastunirman Vrundavan Park?
Vastunirman Vrundavan Park is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Vastunirman Vrundavan Park?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Vastunirman Vrundavan Park: gharkundli.com/tools/property-cost-calculator
Has Vastunirman Vrundavan Park received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Vastunirman Vrundavan Park is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Vastunirman Vrundavan Park uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Vastunirman Vrundavan Park was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Vastunirman Vrundavan Park's possession date changes?
The latest dates are on Vastunirman Vrundavan Park's MahaRERA page (P51700049309). GharKundli's Kundli Watch sends a free WhatsApp update on Vastunirman Vrundavan Park every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vastunirman Vrundavan Park have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunirman Vrundavan Park has 2 buildings filed: JAI - BLDG NO 1 WING A WING B with 8 floors; JUI - BLDG NO 2 WING A WING B WING C with 8 floors.
How big is the land of Vastunirman Vrundavan Park?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunirman Vrundavan Park stands on 3,000 sq m of land (about 0.7 acres), with 6,442 sq m of sanctioned built-up area.
What is the track record of Vastunirman Vrundavan Park's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Vastunirman Developers has 2 projects on MahaRERA since 2023, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 15 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Vastunirman Vrundavan Park?
Google Maps has reviews of Vastunirman Vrundavan Park written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Vastunirman Vrundavan Park?
Vastunirman Vrundavan Park by SHREE VASTUNIRMAN DEVELOPERS is in Devrung, Thane, pincode 421302, Maharashtra, and is registered on MahaRERA as P51700049309, per GharKundli's check of MahaRERA records. Its land is filed as 94/19, 94/23, 94/25. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).
How many flats are in Vastunirman Vrundavan Park?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunirman Vrundavan Park has 70 homes in 2 towers registered on MahaRERA.
When was Vastunirman Vrundavan Park registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vastunirman Vrundavan Park was registered on MahaRERA on 7 February 2023. GharKundli did not find a title report on the land on file there.
Does Vastunirman Vrundavan Park have any legal issues or court cases?
No court cases are listed for Vastunirman Vrundavan Park on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Vastunirman Vrundavan Park?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE VASTUNIRMAN DEVELOPERS, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vastunirman Vrundavan Park
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Bhiwandi
- Vrundavan
- Ashoka Complex
- Kohinoor Uptown T1 & T6
- Neelkanth Sadan
- Regal Square PH 4 Tower 6 and 8
- Sai Deep Residency
- The Pallazo
- Royal Park
Other projects by SHREE VASTUNIRMAN DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.