Sai Ram Heights

by SAI RAM BUILDERS AND DEVELOPERS · Devrund, Thane 421302

What’s in the report? →

Possession date of Sai Ram Heights (MahaRERA P51700076874): 30 April 2027, moved from 31 March 2025 (21 months later). It has 115 homes, 21% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700076874, and currently active. Its completion date has moved from March 2025 to April 2027: 21 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700076874, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Sai Ram Heights?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Sai Ram Heights has moved

  1. 31 March 2025

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA24062501726)

    Reason the builder gave MahaRERA:
    “The Commencement Certificate was issued on 05/04/2024 only. At the time of registration we have estimated to complete the project in one year but we will need one and half year more to complete the project. We request you to kindly grant us…” Read the full reason“The Commencement Certificate was issued on 05/04/2024 only. At the time of registration we have estimated to complete the project in one year but we will need one and half year more to complete the project. We request you to kindly grant us extension till 31 December 2026.”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Sai Ram Heights’s extension records on MahaRERA (P51700076874), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sai Ram Heights

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700076874
Status
Registered and active
Builder
SAI RAM BUILDERS AND DEVELOPERS
Location
Devrund, Thane · 421302
Project type
Residential / Group Housing
Registered on
3 Jul 2024
Completion date at registration
March 2025
Latest completion date
April 2027
Delay so far
21 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
115
Sold or booked
21%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Sai Ram Heights, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A AND B WING100%100%100%100%
C WING100%100%65%65%

Commencement certificate (CC), as filed on MahaRERA

  • A AND B WING: covers 7 floors
  • C WING: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Ram Heights every 1–2 months.

Sai Ram Heights: buildings, flats and land, as filed on MahaRERA

  • Buildings: A AND B WING (8 floors, 87 units) · C WING (8 floors, 28 units)
  • Car parking: 48 covered, 66 open
  • Land: 3,000 sq m (about 0.7 acres) · sanctioned built-up 6,203 sq m
  • Land, as filed: S NO 77 H NO 3
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Sai Ram Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sai Ram Heights: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Sai Ram Heights

What is the possession date of Sai Ram Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sai Ram Heights in Devrund, Thane is 30 April 2027 — 21 months later than 31 March 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 21 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Sai Ram Heights?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Ram Heights's builder has filed on MahaRERA, the official one, is 30 April 2027, already 21 months later than the 31 March 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sai Ram Heights extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Ram Heights's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The Commencement Certificate was issued on 05/04/2024 only. At the time of registration we have estimated to complete the project in one year but we will need one and half year more to complete the project. We request you to kindly grant us extension till 31 December 2026.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Sai Ram Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sai Ram Heights in Devrund, Thane is P51700076874.

Is Sai Ram Heights registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Ram Heights is registered as P51700076874 and its status is "Registered and active".

What is the current construction status of Sai Ram Heights? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Ram Heights's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Sai Ram Heights have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Sai Ram Heights safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Ram Heights is registered on MahaRERA as P51700076874, its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Sai Ram Heights?

Sai Ram Heights is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Sai Ram Heights?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sai Ram Heights: gharkundli.com/tools/property-cost-calculator

Has Sai Ram Heights received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sai Ram Heights is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Sai Ram Heights uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sai Ram Heights was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Sai Ram Heights's possession date changes?

The latest dates are on Sai Ram Heights's MahaRERA page (P51700076874). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Ram Heights every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sai Ram Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Ram Heights has 2 buildings filed: A AND B WING with 8 floors and 87 units; C WING with 8 floors and 28 units.

How much parking does Sai Ram Heights have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 48 covered and 66 open car parking spaces for Sai Ram Heights.

How big is the land of Sai Ram Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Ram Heights stands on 3,000 sq m of land (about 0.7 acres), with 6,203 sq m of sanctioned built-up area.

What are the reviews of Sai Ram Heights?

Google Maps has reviews of Sai Ram Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Sai Ram Heights?

Sai Ram Heights by SAI RAM BUILDERS AND DEVELOPERS is in Devrund, Thane, pincode 421302, Maharashtra, and is registered on MahaRERA as P51700076874, per GharKundli's check of MahaRERA records. Its land is filed as S NO 77 H NO 3. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Sai Ram Heights, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Ram Heights has 115 homes in 2 towers registered on MahaRERA, and 21% of them are sold or booked.

When was Sai Ram Heights registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Sai Ram Heights was registered on MahaRERA on 3 July 2024. GharKundli did not find a title report on the land on file there.

Does Sai Ram Heights have any legal issues or court cases?

No court cases are listed for Sai Ram Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Sai Ram Heights?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAI RAM BUILDERS AND DEVELOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Thane →

Other projects in Bhiwandi

All 382 projects in Bhiwandi (421302) →

Other projects by SAI RAM BUILDERS AND DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.