Skip to content
GharKundli

Giriraj Sarvoday Greens Phase 3

by GIRIRAJ REALTORS · Village Temghar, Thane 421302Also near Bhiwandi, BhadwadRegistered on MahaRERA as “Sarvoday Greens Phase 3”

What’s in the report? →

Possession date of Giriraj Sarvoday Greens Phase 3 (MahaRERA P51700079144): 31 July 2028. It has 187 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700079144, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51700079144, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Giriraj Sarvoday Greens Phase 3?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Giriraj Sarvoday Greens Phase 3 has moved

  1. 31 March 2028

    Completion date given when the project was registered

  2. 31 July 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Giriraj Sarvoday Greens Phase 3’s extension records on MahaRERA (P51700079144), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Giriraj Sarvoday Greens Phase 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700079144
Status
Registered and active
Builder
GIRIRAJ REALTORS
Location
Village Temghar, Thane · 421302
Project type
Residential / Group Housing
Registered on
10 Feb 2025
Completion date at registration
March 2028
Latest completion date
July 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
187
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Giriraj Sarvoday Greens Phase 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BLDG NO 30%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Giriraj Sarvoday Greens Phase 3 every 1–2 months.

Giriraj Sarvoday Greens Phase 3: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Giriraj Realtors has 3 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Giriraj Sarvoday Greens Phase 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Giriraj Sarvoday Greens Phase 3: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Giriraj Sarvoday Greens Phase 3

What is the possession date of Giriraj Sarvoday Greens Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Giriraj Sarvoday Greens Phase 3 in Village Temghar, Thane is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Giriraj Sarvoday Greens Phase 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Giriraj Sarvoday Greens Phase 3's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Giriraj Sarvoday Greens Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Giriraj Sarvoday Greens Phase 3 in Village Temghar, Thane is P51700079144.

Is Giriraj Sarvoday Greens Phase 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Giriraj Sarvoday Greens Phase 3 is registered as P51700079144 and its status is "Registered and active".

What is the current construction status of Giriraj Sarvoday Greens Phase 3? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Giriraj Sarvoday Greens Phase 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BLDG NO 3 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does Giriraj Sarvoday Greens Phase 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Giriraj Sarvoday Greens Phase 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Giriraj Sarvoday Greens Phase 3 is registered on MahaRERA as P51700079144, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Giriraj Sarvoday Greens Phase 3?

Giriraj Sarvoday Greens Phase 3 is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Giriraj Sarvoday Greens Phase 3?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Giriraj Sarvoday Greens Phase 3: gharkundli.com/tools/property-cost-calculator

Has Giriraj Sarvoday Greens Phase 3 received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Giriraj Sarvoday Greens Phase 3 is still under construction, with 31 July 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Giriraj Sarvoday Greens Phase 3 uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Giriraj Sarvoday Greens Phase 3 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Giriraj Sarvoday Greens Phase 3's possession date changes?

The latest dates are on Giriraj Sarvoday Greens Phase 3's MahaRERA page (P51700079144). GharKundli's Kundli Watch sends a free WhatsApp update on Giriraj Sarvoday Greens Phase 3 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Giriraj Sarvoday Greens Phase 3 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Giriraj Sarvoday Greens Phase 3 has one building filed: BLDG NO 3 with 20 floors.

How big is the land of Giriraj Sarvoday Greens Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Giriraj Sarvoday Greens Phase 3 stands on 625 sq m of land (about 0.2 acres), with 12,162 sq m of sanctioned built-up area.

What is the track record of Giriraj Sarvoday Greens Phase 3's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Giriraj Realtors has 3 projects on MahaRERA since 2020, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Giriraj Sarvoday Greens Phase 3?

Google Maps has reviews of Giriraj Sarvoday Greens Phase 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Giriraj Sarvoday Greens Phase 3?

Giriraj Sarvoday Greens Phase 3 by GIRIRAJ REALTORS is in Village Temghar, Thane, pincode 421302 (near Bhiwandi, Bhadwad), Maharashtra, and is registered on MahaRERA as P51700079144, per GharKundli's check of MahaRERA records. Its land is filed as S. No. 107/2, 110/1/6, 110/1/7, 110/2, 90/3, 89/2, 90/4, 107/1. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Giriraj Sarvoday Greens Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), Giriraj Sarvoday Greens Phase 3 has 187 homes in 1 tower registered on MahaRERA.

When was Giriraj Sarvoday Greens Phase 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Giriraj Sarvoday Greens Phase 3 was registered on MahaRERA on 10 February 2025. GharKundli did not find a title report on the land on file there.

Does Giriraj Sarvoday Greens Phase 3 have any legal issues or court cases?

No court cases are listed for Giriraj Sarvoday Greens Phase 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Giriraj Sarvoday Greens Phase 3?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is GIRIRAJ REALTORS, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Bhiwandi

All 382 projects in Bhiwandi (421302) →

Other projects by GIRIRAJ REALTORS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.