Skip to content
GharKundli

Arbisha Apartment

by ARBISHA CONSTRUCTION · Village Nizampur, Thane 421302

What’s in the report? →

Possession date of Arbisha Apartment (MahaRERA PR1330002501802): 30 April 2033. It has 56 homes, 0% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under PR1330002501802, and currently active. Its completion date is now April 2033, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for PR1330002501802, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Arbisha Apartment?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Arbisha Apartment has moved

  1. 31 December 2032

    Completion date given when the project was registered

  2. 30 April 2033

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Arbisha Apartment’s extension records on MahaRERA (PR1330002501802), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Arbisha Apartment

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2033 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PR1330002501802
Status
Registered and active
Builder
ARBISHA CONSTRUCTION
Location
Village Nizampur, Thane · 421302
Project type
Residential / Group Housing
Registered on
16 Dec 2025
Completion date at registration
December 2032
Latest completion date
April 2033
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
56
Sold or booked
0%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Arbisha Apartment, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Arbisha Apartment / A WING0%0%0%0%
Arbisha Apartment / B WING0%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • Arbisha Apartment: covers 8 floors
  • Arbisha Apartment: covers 8 floors

Latest CC order on MahaRERA: dated 21/05/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Arbisha Apartment every 1–2 months.

Arbisha Apartment: buildings, flats and land, as filed on MahaRERA

  • Buildings: Arbisha Apartment (8 floors, 31 units) · Arbisha Apartment (8 floors, 28 units)
  • Car parking: 24 covered
  • Land: 1,241 sq m (about 0.3 acres) · sanctioned built-up 4,390 sq m
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Arbisha Apartment →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Arbisha Apartment: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Arbisha Apartment

What is the possession date of Arbisha Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Arbisha Apartment in Village Nizampur, Thane is 30 April 2033, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Arbisha Apartment?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Arbisha Apartment's builder has filed on MahaRERA, the official one, is 30 April 2033, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Arbisha Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Arbisha Apartment in Village Nizampur, Thane is PR1330002501802.

Is Arbisha Apartment registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Arbisha Apartment is registered as PR1330002501802 and its status is "Registered and active".

What is the current construction status of Arbisha Apartment? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Arbisha Apartment's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Arbisha Apartment have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Arbisha Apartment safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Arbisha Apartment is registered on MahaRERA as PR1330002501802, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Arbisha Apartment?

Arbisha Apartment is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Arbisha Apartment?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Arbisha Apartment: gharkundli.com/tools/property-cost-calculator

Has Arbisha Apartment received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Arbisha Apartment is still under construction, with 30 April 2033 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Arbisha Apartment uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Arbisha Apartment was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Arbisha Apartment's possession date changes?

The latest dates are on Arbisha Apartment's MahaRERA page (PR1330002501802). GharKundli's Kundli Watch sends a free WhatsApp update on Arbisha Apartment every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Arbisha Apartment have?

According to GharKundli's check of MahaRERA records (updated October 2026), Arbisha Apartment has 2 buildings filed: Arbisha Apartment with 8 floors and 31 units; Arbisha Apartment with 8 floors and 28 units.

How much parking does Arbisha Apartment have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 24 covered car parking spaces for Arbisha Apartment.

How big is the land of Arbisha Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), Arbisha Apartment stands on 1,241 sq m of land (about 0.3 acres), with 4,390 sq m of sanctioned built-up area.

What are the reviews of Arbisha Apartment?

Google Maps has reviews of Arbisha Apartment written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Arbisha Apartment?

Arbisha Apartment by ARBISHA CONSTRUCTION is in Village Nizampur, Thane, pincode 421302, Maharashtra, and is registered on MahaRERA as PR1330002501802, per GharKundli's check of MahaRERA records. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Arbisha Apartment, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Arbisha Apartment has 56 homes in 2 towers registered on MahaRERA, and 0% of them are sold or booked.

When was Arbisha Apartment registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Arbisha Apartment was registered on MahaRERA on 16 December 2025. GharKundli did not find a title report on the land on file there.

Does Arbisha Apartment have any legal issues or court cases?

No court cases are listed for Arbisha Apartment on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Arbisha Apartment?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARBISHA CONSTRUCTION.

Other projects in Bhiwandi

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.