Possession date of Samarth Residency: 28 April 2029, moved from 30 December 2021 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000006942, and currently active. Its completion date has moved from December 2021 to April 2029: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Samarth Residency?
How the possession date of Samarth Residency has moved
30 December 2021
Completion date given when the project was registered
28 December 2028
Extended at the builder's request (MahaRERA application EXT52000011202)
Reason the builder gave MahaRERA:
“Project “SAMARTH RESTANCY “Completed ‘WING B ‘successfully. ‘WING B ‘ OC (Occupancy Certificate) obtained Outward No. 888 /18-19 dated 27/02/2019 (Documents attached) and Form 4_ Architect Certificate document attached. “WING A” constructio…” Read the full reason
“Project “SAMARTH RESTANCY “Completed ‘WING B ‘successfully. ‘WING B ‘ OC (Occupancy Certificate) obtained Outward No. 888 /18-19 dated 27/02/2019 (Documents attached) and Form 4_ Architect Certificate document attached. “WING A” construction work with levelling of land was started, but due to COVID – 19 situation the further construction work had been delayed with uncertain COVID-19 period, like – Shortage of Labour at site, un even transport of materials required, Materials Shortage ,etc… for Building construction etc… Hence we about to continue out ongoing ‘WING-A’, Building construction.…”28 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Samarth Residency’s extension records on MahaRERA (P52000006942), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Samarth Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000006942
- Status
- Registered and active
- Builder
- Aryan Realtors
- Location
- Pratiksha Nagar, Sion, Raigarh · 410201
- Project type
- Residential / Group Housing
- Registered on
- 16 Aug 2017
- Completion date at registration
- December 2021
- Latest completion date
- April 2029
- Delay so far
- 84 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 68
- Sold or booked
- 30%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Samarth Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Samarth Residency B wing | 100% | 100% | 100% | 100% |
| Samarth Residency A wing | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Samarth Residency B wing: covers Stilt+Ground+4Floors
- Samarth Residency A wing: covers GROUND,FIRST,SECOND AND THIRD,FOURTH,FIFTH SIXTH AND SEVENTH
Latest CC order on MahaRERA: dated 20/05/2024.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Samarth Residency every month.
Samarth Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: Samarth Residency B wing (6 floors, 24 units) · Samarth Residency A wing (8 floors, 56 units)
- Car parking: 15 covered, 2 open
- Land: 1,392 sq m (about 0.3 acres) · sanctioned built-up 2,932 sq m
- Boundaries filed include: Karjat Gundge Road, Boundary of Nagar Parishad
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Samarth Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Samarth Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Samarth Residency
What is the possession date of Samarth Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Samarth Residency in Pratiksha Nagar, Sion, Raigarh is 28 April 2029 — 84 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Samarth Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Samarth Residency's builder has filed on MahaRERA, the official one, is 28 April 2029, already 84 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Samarth Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Residency's builder applied to MahaRERA to extend the completion date once: to 28 December 2028, giving the reason "Project “SAMARTH RESTANCY “Completed ‘WING B ‘successfully. ‘WING B ‘ OC (Occupancy Certificate) obtained Outward No. 888 /18-19 dated 27/02/2019 (Documents attached) and Form 4_ Architect Certificate document attached. “WING A” construction work with levelling of land was started, but due to COVID – 19 situation the further construction work had been delayed with uncertain COVID-19 period, like – Shortage of Labour at site, un even transport of materials required, Materials Shortage ,etc… for Building construction etc… Hence we about to continue out ongoing ‘WING-A’, Building construction.…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Samarth Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Samarth Residency in Pratiksha Nagar, Sion, Raigarh is P52000006942.
Is Samarth Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Residency is registered as P52000006942 and its status is "Registered and active".
What is the construction status of Samarth Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Samarth Residency have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Samarth Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Residency is registered on MahaRERA as P52000006942, its completion date has moved 84 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Samarth Residency's possession date changes?
The latest dates are on Samarth Residency's MahaRERA page (P52000006942). GharKundli's Kundli Watch sends a free WhatsApp update on Samarth Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Samarth Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Residency has 2 buildings filed: Samarth Residency B wing with 6 floors and 24 units; Samarth Residency A wing with 8 floors and 56 units.
How much parking does Samarth Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 covered and 2 open car parking spaces for Samarth Residency.
How big is the land of Samarth Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Residency stands on 1,392 sq m of land (about 0.3 acres), with 2,932 sq m of sanctioned built-up area.
Where can I read reviews of Samarth Residency?
Google Maps has reviews of Samarth Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Samarth Residency?
Samarth Residency by Aryan Realtors is in Pratiksha Nagar, Sion, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000006942, per GharKundli's check of MahaRERA records. Its boundaries filed there include Karjat Gundge Road, Boundary of Nagar Parishad.
How many homes are in Samarth Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Residency has 68 homes in 2 towers registered on MahaRERA, and 30% of them are sold or booked.
When was Samarth Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Samarth Residency was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Samarth Residency?
No court cases are listed for Samarth Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Samarth Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Aryan Realtors.
Check it yourself on MahaRERA
- How to check the possession date of Samarth Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Raigad →
Other projects in Karjat
- SWAMI AASHRAY
- 21 ENCLAVE
- Ratnamisha Villas
- Krishna Valley Phase I
- MUDRA AVENUE
- Hill Top Residency
- Gajvakra Heights
- MIRA RESIDENCY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.