MOUNT VILLE
by M/S SAMVID LIFE SPACES · Lokgram, Raigarh
Possession date of MOUNT VILLE: 30 April 2027, moved from 31 March 2019 (93 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000013152, and currently active. Its completion date has moved from March 2019 to April 2027: 93 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 7 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MOUNT VILLE?
How the possession date of MOUNT VILLE has moved
31 March 2019
Completion date given when the project was registered
30 March 2020
Extended at the builder's request (MahaRERA application EXT52000001711)
Reason the builder gave MahaRERA:
“We are facing the problem of non availability of labour at the local site, Delay in supply of materials from the contractors and vendors, increase in cost of sand. Further we are also facing the financial issue due to delay in disbursement…” Read the full reason
“We are facing the problem of non availability of labour at the local site, Delay in supply of materials from the contractors and vendors, increase in cost of sand. Further we are also facing the financial issue due to delay in disbursement of funds from NBFC i.e. Indiabulls Housing Finance from October, 2018.”30 December 2022
Extended at the builder's request (MahaRERA application EXT52000011525)
Reason the builder gave MahaRERA: “DUE TO COVID PANDEMIC WE ARE UNABLE TO SOLD REMAINING FLAT”
30 June 2024
Extended at the builder's request (MahaRERA application EXT52000017187)
Reason the builder gave MahaRERA: “90% OF THE PROJECT HAS BEEN COMPLETED FOR COMPLETION WE REQUIRED 6 MONTHS TO COMPLETE”
31 December 2026
Extended at the builder's request (MahaRERA application EXT52000024997)
Reason the builder gave MahaRERA: “THERE ARE SOME WORKS REMAINING IN THE PROJECT AND ALSO UNITS HAS NOT BEEN SOLD FULLY THEREFORE PROMOTERS REQUEST FOR EXTENSION OF TIME LIMIT FOR PROJECT”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MOUNT VILLE’s extension records on MahaRERA (P52000013152), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MOUNT VILLE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 7 complaints, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000013152
- Status
- Registered and active
- Builder
- M/S SAMVID LIFE SPACES
- Location
- Lokgram, Raigarh · 410201
- Project type
- Others
- Registered on
- 14 Sep 2017
- Completion date at registration
- March 2019
- Latest completion date
- April 2027
- Delay so far
- 93 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 34
- Towers
- 2
- Complaints on MahaRERA
- 7
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of MOUNT VILLE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| B WING | 100% | 100% | 50% | 25% |
| C WING | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MOUNT VILLE every month.
MOUNT VILLE: buildings, flats and land, as filed on MahaRERA
- Buildings: B WING (5 floors) · C WING (5 floors)
- Land: 1,700 sq m (about 0.4 acres) · sanctioned built-up 895 sq m · recreational space 250 sq m
- Boundaries filed include: KIRVALI VILLAGE ROAD
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MOUNT VILLE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MOUNT VILLE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MOUNT VILLE
What is the possession date of MOUNT VILLE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MOUNT VILLE in Lokgram, Raigarh is 30 April 2027 — 93 months later than 31 March 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MOUNT VILLE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MOUNT VILLE's builder has filed on MahaRERA, the official one, is 30 April 2027, already 93 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MOUNT VILLE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MOUNT VILLE's builder applied to MahaRERA to extend the completion date 4 times: to 30 March 2020, giving the reason "We are facing the problem of non availability of labour at the local site, Delay in supply of materials from the contractors and vendors, increase in cost of sand. Further we are also facing the financial issue due to delay in disbursement of funds from NBFC i.e. Indiabulls Housing Finance from October, 2018."; to 30 December 2022, giving the reason "DUE TO COVID PANDEMIC WE ARE UNABLE TO SOLD REMAINING FLAT"; to 30 June 2024, giving the reason "90% OF THE PROJECT HAS BEEN COMPLETED FOR COMPLETION WE REQUIRED 6 MONTHS TO COMPLETE"; to 31 December 2026, giving the reason "THERE ARE SOME WORKS REMAINING IN THE PROJECT AND ALSO UNITS HAS NOT BEEN SOLD FULLY THEREFORE PROMOTERS REQUEST FOR EXTENSION OF TIME LIMIT FOR PROJECT". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of MOUNT VILLE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MOUNT VILLE in Lokgram, Raigarh is P52000013152.
Is MOUNT VILLE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MOUNT VILLE is registered as P52000013152 and its status is "Registered and active".
What is the construction status of MOUNT VILLE?
According to GharKundli's check of MahaRERA records (updated October 2026), MOUNT VILLE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does MOUNT VILLE have complaints on MahaRERA?
7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is MOUNT VILLE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MOUNT VILLE is registered on MahaRERA as P52000013152, its completion date has moved 93 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MOUNT VILLE's possession date changes?
The latest dates are on MOUNT VILLE's MahaRERA page (P52000013152). GharKundli's Kundli Watch sends a free WhatsApp update on MOUNT VILLE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MOUNT VILLE have?
According to GharKundli's check of MahaRERA records (updated October 2026), MOUNT VILLE has 2 buildings filed: B WING with 5 floors; C WING with 5 floors.
How big is the land of MOUNT VILLE?
According to GharKundli's check of MahaRERA records (updated October 2026), MOUNT VILLE stands on 1,700 sq m of land (about 0.4 acres), with 895 sq m of sanctioned built-up area and 250 sq m of recreational open space.
Where can I read reviews of MOUNT VILLE?
Google Maps has reviews of MOUNT VILLE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MOUNT VILLE?
MOUNT VILLE by M/S SAMVID LIFE SPACES is in Lokgram, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000013152, per GharKundli's check of MahaRERA records. Its boundaries filed there include KIRVALI VILLAGE ROAD.
How many homes are in MOUNT VILLE?
According to GharKundli's check of MahaRERA records (updated October 2026), MOUNT VILLE has 34 homes in 2 towers registered on MahaRERA.
When was MOUNT VILLE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MOUNT VILLE was registered on MahaRERA on 14 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MOUNT VILLE?
No court cases are listed for MOUNT VILLE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MOUNT VILLE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S SAMVID LIFE SPACES.
Check it yourself on MahaRERA
- How to check the possession date of MOUNT VILLE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in Karjat
- SWAMI AASHRAY
- 21 ENCLAVE
- Ratnamisha Villas
- MUDRA AVENUE
- Krishna Valley Phase I
- Hill Top Residency
- Gajvakra Heights
- MIRA RESIDENCY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.