ARIHANT ALOKI PHASE IV
by ARIHANT AASHIYANA PRIVATE LIMITED · Bhisegaon, Raigarh
Possession: ARIHANT ALOKI PHASE IV is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000025041. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ARIHANT ALOKI PHASE IV?
How the possession date of ARIHANT ALOKI PHASE IV has moved
30 December 2025
Completion date given when the project was registered
27 June 2026
Extended at the builder's request (MahaRERA application EA11032620175)
Reason the builder gave MahaRERA:
“As the Promoter of the project, we respectfully submit that the extension is being sought to enable completion of the remaining statutory and procedural formalities required for formal project closure under RERA. While the development work…” Read the full reason
“As the Promoter of the project, we respectfully submit that the extension is being sought to enable completion of the remaining statutory and procedural formalities required for formal project closure under RERA. While the development work has been substantially completed, certain regulatory compliances, final approvals from the concerned authorities, documentation, and handover-related formalities are still in process. Additional time is therefore required to ensure full compliance with the provisions of RERA and to facilitate proper and lawful closure of the project without any procedural…”
Source: ARIHANT ALOKI PHASE IV’s extension records on MahaRERA (P52000025041), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ARIHANT ALOKI PHASE IV
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- ARIHANT ALOKI PHASE IP52000004014 · possession 29 Dec 2021
- ARIHANT ALOKI PHASE IIP52000006314 · possession 30 Mar 2022
- ARIHANT ALOKI PHASE IIIP52000024460 · possession 30 Apr 2025
- ARIHANT ALOKI PHASE IIIP52000019001 · possession 30 Dec 2024
- ARIHANT ALOKI PHASE VP52000025052 · possession 30 Apr 2032
- ARIHANT ALOKI PHASE VIP52000025180 · possession 30 Apr 2032
- MahaRERA registration
- P52000025041
- Status
- Completed
- Builder
- ARIHANT AASHIYANA PRIVATE LIMITED
- Location
- Bhisegaon, Raigarh · 410201
- Project type
- Residential / Group Housing
- Registered on
- 18 Mar 2020
- Completion date at registration
- December 2025
- Latest completion date
- June 2026
- Delay so far
- 6 months
- Homes
- 141
- Sold or booked
- 61%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 11
Construction progress of ARIHANT ALOKI PHASE IV, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A3 | 100% | 100% | 91% | 70% |
Commencement certificate (CC), as filed on MahaRERA
- A3: covers 16 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARIHANT ALOKI PHASE IV every month.
ARIHANT ALOKI PHASE IV: buildings, flats and land, as filed on MahaRERA
- Buildings: A3 (16 floors, 141 units)
- Car parking: 1 covered
- Land: 5,323 sq m (about 1.3 acres) · sanctioned built-up 3,684 sq m · recreational space 532 sq m
The builder’s record and reviews
Arihant Superstructures (a group of 7 linked companies) has 45 projects on MahaRERA since 2017, this one included. Of the 45 GharKundli has checked: 23 finished, 20 within the promised date and 3 needed more time (typically 6 months); 21 still being built, none past the promised date yet; 1 lapsed. 67 complaints on MahaRERA across 24 projects.
Read Google reviews of ARIHANT ALOKI PHASE IV →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ARIHANT ALOKI PHASE IV: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ARIHANT ALOKI PHASE IV
What is the possession date of ARIHANT ALOKI PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARIHANT ALOKI PHASE IV in Bhisegaon, Raigarh is 27 June 2026 — 6 months later than 30 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for ARIHANT ALOKI PHASE IV?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ARIHANT ALOKI PHASE IV's builder has filed on MahaRERA, the official one, is 27 June 2026, already 6 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ARIHANT ALOKI PHASE IV extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE IV's builder applied to MahaRERA to extend the completion date once: to 27 June 2026, giving the reason "As the Promoter of the project, we respectfully submit that the extension is being sought to enable completion of the remaining statutory and procedural formalities required for formal project closure under RERA. While the development work has been substantially completed, certain regulatory compliances, final approvals from the concerned authorities, documentation, and handover-related formalities are still in process. Additional time is therefore required to ensure full compliance with the provisions of RERA and to facilitate proper and lawful closure of the project without any procedural…".
What is the RERA number of ARIHANT ALOKI PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ARIHANT ALOKI PHASE IV in Bhisegaon, Raigarh is P52000025041.
Is ARIHANT ALOKI PHASE IV registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE IV is registered as P52000025041 and its status is "Completed".
What is the construction status of ARIHANT ALOKI PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE IV's status on MahaRERA is "Completed". As filed by the builder, slab work on A3 is 100% done and internal work 91%. GharKundli's full report compares construction progress with the deadline.
Does ARIHANT ALOKI PHASE IV have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ARIHANT ALOKI PHASE IV safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE IV is registered on MahaRERA as P52000025041, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does ARIHANT ALOKI PHASE IV have other wings or phases?
Yes. MahaRERA lists 6 other registrations of the same project, each with its own possession date: ARIHANT ALOKI PHASE I (P52000004014, possession 29 Dec 2021); ARIHANT ALOKI PHASE II (P52000006314, possession 30 Mar 2022); ARIHANT ALOKI PHASE III (P52000024460, possession 30 Apr 2025); ARIHANT ALOKI PHASE III (P52000019001, possession 30 Dec 2024); ARIHANT ALOKI PHASE V (P52000025052, possession 30 Apr 2032); ARIHANT ALOKI PHASE VI (P52000025180, possession 30 Apr 2032). Check that your agreement names the registration of your own wing.
How can I get updates if ARIHANT ALOKI PHASE IV's possession date changes?
The latest dates are on ARIHANT ALOKI PHASE IV's MahaRERA page (P52000025041). GharKundli's Kundli Watch sends a free WhatsApp update on ARIHANT ALOKI PHASE IV every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ARIHANT ALOKI PHASE IV have?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE IV has one building filed: A3 with 16 floors and 141 units.
How much parking does ARIHANT ALOKI PHASE IV have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for ARIHANT ALOKI PHASE IV.
How big is the land of ARIHANT ALOKI PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE IV stands on 5,323 sq m of land (about 1.3 acres), with 3,684 sq m of sanctioned built-up area and 532 sq m of recreational open space.
What is the track record of ARIHANT ALOKI PHASE IV's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Arihant Superstructures (a group of 7 linked companies) has 45 projects on MahaRERA since 2017, this one included. Of the 45 GharKundli has checked: 23 finished, 20 within the promised date and 3 needed more time (typically 6 months); 21 still being built, none past the promised date yet; 1 lapsed. 67 complaints on MahaRERA across 24 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ARIHANT ALOKI PHASE IV?
Google Maps has reviews of ARIHANT ALOKI PHASE IV written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ARIHANT ALOKI PHASE IV?
ARIHANT ALOKI PHASE IV by ARIHANT AASHIYANA PRIVATE LIMITED is in Bhisegaon, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000025041, per GharKundli's check of MahaRERA records.
How many homes are in ARIHANT ALOKI PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE IV has 141 homes in 1 tower registered on MahaRERA, and 61% of them are sold or booked.
When was ARIHANT ALOKI PHASE IV registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE IV was registered on MahaRERA on 18 March 2020. GharKundli did not find a title report on the land on file there.
Are there court cases on ARIHANT ALOKI PHASE IV?
2 court cases are listed for ARIHANT ALOKI PHASE IV on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of ARIHANT ALOKI PHASE IV?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT AASHIYANA PRIVATE LIMITED, which has 11 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of ARIHANT ALOKI PHASE IV
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 410201
- HOLIDAY MAIYAAN KARJAT
- RIVA RYTHM -I, J,K,L WING
- Krishna Valley Phase I
- Gajvakra Heights
- 21 ENCLAVE
- MUDRA AVENUE
- Hill Top Residency
- Ratnamisha Villas
Other projects by ARIHANT AASHIYANA PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.