ARIHANT ALOKI PHASE V

by ARIHANT AASHIYANA PRIVATE LIMITED · karjat, Raigarh

Possession date of ARIHANT ALOKI PHASE V: 30 April 2032, moved from 30 December 2026 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000025052, and currently active. Its completion date has moved from December 2026 to April 2032: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about ARIHANT ALOKI PHASE V?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of ARIHANT ALOKI PHASE V has moved

  1. 30 December 2026

    Completion date given when the project was registered

  2. 31 December 2031

    Extended at the builder's request (MahaRERA application EXT52000024554)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”
  3. 30 April 2032

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: ARIHANT ALOKI PHASE V’s extension records on MahaRERA (P52000025052), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on ARIHANT ALOKI PHASE V

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint and 2 court cases, and how it ended
  • Construction pace against the April 2032 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000025052
Status
Registered and active
Builder
ARIHANT AASHIYANA PRIVATE LIMITED
Location
karjat, Raigarh · 410201
Project type
Residential / Group Housing
Registered on
18 Mar 2020
Completion date at registration
December 2026
Latest completion date
April 2032
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
142
Sold or booked
0%
Towers
1
Complaints on MahaRERA
1
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
11

Construction progress of ARIHANT ALOKI PHASE V, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
C10%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • C1: covers 17 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on ARIHANT ALOKI PHASE V every month.

ARIHANT ALOKI PHASE V: buildings, flats and land, as filed on MahaRERA

  • Buildings: C1 (17 floors, 142 units)
  • Car parking: 1 covered
  • Land: 2,808 sq m (about 0.7 acres) · sanctioned built-up 8,097 sq m · recreational space 380 sq m

The builder’s record and reviews

Arihant Superstructures (a group of 7 linked companies) has 45 projects on MahaRERA since 2017, this one included. Of the 45 GharKundli has checked: 23 finished, 20 within the promised date and 3 needed more time (typically 6 months); 21 still being built, none past the promised date yet; 1 lapsed. 67 complaints on MahaRERA across 24 projects.

Read Google reviews of ARIHANT ALOKI PHASE V →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

ARIHANT ALOKI PHASE V: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about ARIHANT ALOKI PHASE V

What is the possession date of ARIHANT ALOKI PHASE V?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ARIHANT ALOKI PHASE V in karjat, Raigarh is 30 April 2032 — 60 months later than 30 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for ARIHANT ALOKI PHASE V?

Builders and listing sites often quote an earlier "target" date for handover. The completion date ARIHANT ALOKI PHASE V's builder has filed on MahaRERA, the official one, is 30 April 2032, already 60 months later than the 30 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of ARIHANT ALOKI PHASE V extended?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE V's builder applied to MahaRERA to extend the completion date once: to 31 December 2031, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of ARIHANT ALOKI PHASE V?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ARIHANT ALOKI PHASE V in karjat, Raigarh is P52000025052.

Is ARIHANT ALOKI PHASE V registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE V is registered as P52000025052 and its status is "Registered and active".

What is the construction status of ARIHANT ALOKI PHASE V?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE V's status on MahaRERA is "Registered and active". As filed by the builder, slab work on C1 is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does ARIHANT ALOKI PHASE V have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is ARIHANT ALOKI PHASE V safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE V is registered on MahaRERA as P52000025052, its completion date has moved 60 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does ARIHANT ALOKI PHASE V have other wings or phases?

Yes. MahaRERA lists 6 other registrations of the same project, each with its own possession date: ARIHANT ALOKI PHASE I (P52000004014, possession 29 Dec 2021); ARIHANT ALOKI PHASE II (P52000006314, possession 30 Mar 2022); ARIHANT ALOKI PHASE III (P52000024460, possession 30 Apr 2025); ARIHANT ALOKI PHASE III (P52000019001, possession 30 Dec 2024); ARIHANT ALOKI PHASE IV (P52000025041, possession 27 Jun 2026); ARIHANT ALOKI PHASE VI (P52000025180, possession 30 Apr 2032). Check that your agreement names the registration of your own wing.

How can I get updates if ARIHANT ALOKI PHASE V's possession date changes?

The latest dates are on ARIHANT ALOKI PHASE V's MahaRERA page (P52000025052). GharKundli's Kundli Watch sends a free WhatsApp update on ARIHANT ALOKI PHASE V every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does ARIHANT ALOKI PHASE V have?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE V has one building filed: C1 with 17 floors and 142 units.

How much parking does ARIHANT ALOKI PHASE V have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for ARIHANT ALOKI PHASE V.

How big is the land of ARIHANT ALOKI PHASE V?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE V stands on 2,808 sq m of land (about 0.7 acres), with 8,097 sq m of sanctioned built-up area and 380 sq m of recreational open space.

What is the track record of ARIHANT ALOKI PHASE V's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Arihant Superstructures (a group of 7 linked companies) has 45 projects on MahaRERA since 2017, this one included. Of the 45 GharKundli has checked: 23 finished, 20 within the promised date and 3 needed more time (typically 6 months); 21 still being built, none past the promised date yet; 1 lapsed. 67 complaints on MahaRERA across 24 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of ARIHANT ALOKI PHASE V?

Google Maps has reviews of ARIHANT ALOKI PHASE V written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is ARIHANT ALOKI PHASE V?

ARIHANT ALOKI PHASE V by ARIHANT AASHIYANA PRIVATE LIMITED is in karjat, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000025052, per GharKundli's check of MahaRERA records.

How many homes are in ARIHANT ALOKI PHASE V?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE V has 142 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was ARIHANT ALOKI PHASE V registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), ARIHANT ALOKI PHASE V was registered on MahaRERA on 18 March 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on ARIHANT ALOKI PHASE V?

2 court cases are listed for ARIHANT ALOKI PHASE V on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of ARIHANT ALOKI PHASE V?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ARIHANT AASHIYANA PRIVATE LIMITED, which has 11 other projects registered on MahaRERA.

Other projects in pincode 410201

All 311 projects in Karjat (410201) →

Other projects by ARIHANT AASHIYANA PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.