KURLA SAHAYOG CHS LTD., BLDG. NO.68
by PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED · Nehru Nagar, MumbaiAlso near Kurla East, Kurla West, Chembur
Possession: KURLA SAHAYOG CHS LTD., BLDG. NO.68 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800009819. Status: Completed. MahaRERA has issued 2 regulatory orders on this project. 7 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about KURLA SAHAYOG CHS LTD., BLDG. NO.68?
How the possession date of KURLA SAHAYOG CHS LTD., BLDG. NO.68 has moved
30 June 2018
Completion date given when the project was registered
30 June 2024
Extended at the builder's request (MahaRERA application EXT51800017825)
Reason the builder gave MahaRERA:
“we are not able to obtain the Undertaking from the Members of the society and allottees which is required for the occupancy certificate. Hence, even if we have completed our construction activities, we are not able to obtain the Occupancy C…” Read the full reason
“we are not able to obtain the Undertaking from the Members of the society and allottees which is required for the occupancy certificate. Hence, even if we have completed our construction activities, we are not able to obtain the Occupancy Certificate.”30 June 2025
Extended at the builder's request (MahaRERA application EXT51800027095)
Reason the builder gave MahaRERA:
“1. When we started the process of the application for the Occupancy Certificate, the MCGM demanded the Undertaking from the members of the society stating that if any further dues will arise the Society will be liable for the same. 2. We ha…” Read the full reason
“1. When we started the process of the application for the Occupancy Certificate, the MCGM demanded the Undertaking from the members of the society stating that if any further dues will arise the Society will be liable for the same. 2. We had already paid necessary dues related to our project to the MCGM and the same has been intimated by us to the society members. 3. Due to a lack of awareness, among the society members and fear of contingent liabilities in future, the members of the society are not ready to sign such an undertaking, hence we are not able to proceed with the Process of the…”
Source: KURLA SAHAYOG CHS LTD., BLDG. NO.68’s extension records on MahaRERA (P51800009819), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on KURLA SAHAYOG CHS LTD., BLDG. NO.68
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 7 complaints, and how it ended
- Construction pace against the June 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800009819
- Status
- Completed
- Builder
- PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED
- Location
- Nehru Nagar, Mumbai · 400024
- Project type
- Residential / Group Housing
- Registered on
- 22 Aug 2017
- Completion date at registration
- June 2018
- Latest completion date
- June 2025
- Delay so far
- 84 months
- Homes
- 43
- Towers
- 1
- Complaints on MahaRERA
- 7
- Court cases listed
- 0
- Appeals at the tribunal
- 3
- MahaRERA regulatory orders
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of KURLA SAHAYOG CHS LTD., BLDG. NO.68, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| KURLA SAHAYOG CHS LTD BLDG NO 68 | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on KURLA SAHAYOG CHS LTD., BLDG. NO.68 every month.
KURLA SAHAYOG CHS LTD., BLDG. NO.68: buildings, flats and land, as filed on MahaRERA
- Buildings: KURLA SAHAYOG CHS LTD BLDG NO 68 (16 floors)
- Land: 856 sq m (about 0.2 acres) · sanctioned built-up 4,013 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Parsn Construction AND Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 57 months); 6 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 18 complaints on MahaRERA across 3 projects.
Read Google reviews of KURLA SAHAYOG CHS LTD., BLDG. NO.68 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
KURLA SAHAYOG CHS LTD., BLDG. NO.68: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about KURLA SAHAYOG CHS LTD., BLDG. NO.68
What is the possession date of KURLA SAHAYOG CHS LTD., BLDG. NO.68?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KURLA SAHAYOG CHS LTD., BLDG. NO.68 in Nehru Nagar, Mumbai is 30 June 2025 — 84 months later than 30 June 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for KURLA SAHAYOG CHS LTD., BLDG. NO.68?
Builders and listing sites often quote an earlier "target" date for handover. The completion date KURLA SAHAYOG CHS LTD., BLDG. NO.68's builder has filed on MahaRERA, the official one, is 30 June 2025, already 84 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of KURLA SAHAYOG CHS LTD., BLDG. NO.68 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), KURLA SAHAYOG CHS LTD., BLDG. NO.68's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2024, giving the reason "we are not able to obtain the Undertaking from the Members of the society and allottees which is required for the occupancy certificate. Hence, even if we have completed our construction activities, we are not able to obtain the Occupancy Certificate."; to 30 June 2025, giving the reason "1. When we started the process of the application for the Occupancy Certificate, the MCGM demanded the Undertaking from the members of the society stating that if any further dues will arise the Society will be liable for the same. 2. We had already paid necessary dues related to our project to the MCGM and the same has been intimated by us to the society members. 3. Due to a lack of awareness, among the society members and fear of contingent liabilities in future, the members of the society are not ready to sign such an undertaking, hence we are not able to proceed with the Process of the…".
What is the RERA number of KURLA SAHAYOG CHS LTD., BLDG. NO.68?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KURLA SAHAYOG CHS LTD., BLDG. NO.68 in Nehru Nagar, Mumbai is P51800009819.
Is KURLA SAHAYOG CHS LTD., BLDG. NO.68 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KURLA SAHAYOG CHS LTD., BLDG. NO.68 is registered as P51800009819 and its status is "Completed".
What is the construction status of KURLA SAHAYOG CHS LTD., BLDG. NO.68?
According to GharKundli's check of MahaRERA records (updated October 2026), KURLA SAHAYOG CHS LTD., BLDG. NO.68's status on MahaRERA is "Completed". As filed by the builder, slab work on KURLA SAHAYOG CHS LTD BLDG NO 68 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does KURLA SAHAYOG CHS LTD., BLDG. NO.68 have complaints on MahaRERA?
7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is KURLA SAHAYOG CHS LTD., BLDG. NO.68 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), KURLA SAHAYOG CHS LTD., BLDG. NO.68 is registered on MahaRERA as P51800009819, its MahaRERA status is "Completed", its completion date has moved 84 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if KURLA SAHAYOG CHS LTD., BLDG. NO.68's possession date changes?
The latest dates are on KURLA SAHAYOG CHS LTD., BLDG. NO.68's MahaRERA page (P51800009819). GharKundli's Kundli Watch sends a free WhatsApp update on KURLA SAHAYOG CHS LTD., BLDG. NO.68 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does KURLA SAHAYOG CHS LTD., BLDG. NO.68 have?
According to GharKundli's check of MahaRERA records (updated October 2026), KURLA SAHAYOG CHS LTD., BLDG. NO.68 has one building filed: KURLA SAHAYOG CHS LTD BLDG NO 68 with 16 floors.
How big is the land of KURLA SAHAYOG CHS LTD., BLDG. NO.68?
According to GharKundli's check of MahaRERA records (updated October 2026), KURLA SAHAYOG CHS LTD., BLDG. NO.68 stands on 856 sq m of land (about 0.2 acres), with 4,013 sq m of sanctioned built-up area.
What is the track record of KURLA SAHAYOG CHS LTD., BLDG. NO.68's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Construction AND Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 57 months); 6 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 18 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of KURLA SAHAYOG CHS LTD., BLDG. NO.68?
Google Maps has reviews of KURLA SAHAYOG CHS LTD., BLDG. NO.68 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is KURLA SAHAYOG CHS LTD., BLDG. NO.68?
KURLA SAHAYOG CHS LTD., BLDG. NO.68 by PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED is in Nehru Nagar, Mumbai (pincode 400024), near Kurla East, Kurla West, Chembur, Maharashtra, and is registered on MahaRERA as P51800009819, per GharKundli's check of MahaRERA records.
How many homes are in KURLA SAHAYOG CHS LTD., BLDG. NO.68?
According to GharKundli's check of MahaRERA records (updated October 2026), KURLA SAHAYOG CHS LTD., BLDG. NO.68 has 43 homes in 1 tower registered on MahaRERA.
When was KURLA SAHAYOG CHS LTD., BLDG. NO.68 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), KURLA SAHAYOG CHS LTD., BLDG. NO.68 was registered on MahaRERA on 22 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on KURLA SAHAYOG CHS LTD., BLDG. NO.68?
No court cases are listed for KURLA SAHAYOG CHS LTD., BLDG. NO.68 on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of KURLA SAHAYOG CHS LTD., BLDG. NO.68?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of KURLA SAHAYOG CHS LTD., BLDG. NO.68
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400024
- SAPTARSHI MARK
- VEER SIDDHANAK CHS LTD
- AMBARISH CHS LTD
- ROHA VATIKA-ROHA KUMUD
- RAGHAV PARIJAT
- Ruparel Crest
- SAYBA TULIP
- DTG APEX
Other projects by PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.