NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62

by PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED · Nehru Nagar, MumbaiAlso near Kurla East, Kurla West, Chembur

Possession date of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62: 31 December 2025, moved from 30 December 2022 (36 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800014914. Status: Lapsed (registration period ended). MahaRERA has issued 2 regulatory orders on this project. 9 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT51800012211)

    Reason the builder gave MahaRERA:
    “Explanatory note regarding the state of development works in the projects and reason for not completing the development works in the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making applicat…” Read the full reason“Explanatory note regarding the state of development works in the projects and reason for not completing the development works in the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making application for the registration of ‘NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62’ – As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 30th DECEMBER 2022 as the project completion date, we will not able to complete the project due to various unavoidable reasons. Such as 1. In 2020 due to the Pandemic situa…”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51800017705)

    Reason the builder gave MahaRERA:
    “1. We received the Offer Letter from MHADA on 13 August 2020 for our Redevelopment project. 2. On 20th June 2020, we paid our premium instalment due, of Rs. 1,45,02,546/- 3. Due to the Covid Pandemic Lockdown Situation, the department delay…” Read the full reason“1. We received the Offer Letter from MHADA on 13 August 2020 for our Redevelopment project. 2. On 20th June 2020, we paid our premium instalment due, of Rs. 1,45,02,546/- 3. Due to the Covid Pandemic Lockdown Situation, the department delayed the issue of the receipt of premium instalment Rs. Rs. 1,45,02,546/-, and the receipt was issued to us on 10th May 2022. 4. Due to such COVID delays, the offer letter lapsed. Hence, MHADA asked us to apply for the revised offer letter. MHADA issued a revised offer letter on 10 May 2022. 5. Also, NOC was required to commence construction activities from…”
  4. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800024814)

    Reason the builder gave MahaRERA: “OC PENDING. Process under progress.”
  5. 31 December 2025

    Extended at the builder's request (MahaRERA application EA21062501691)

    Reason the builder gave MahaRERA:
    “1. We received the Offer Letter from MHADA on 13 August 2020 for our Redevelopment project. 2. On 20th June 2020, we paid our premium instalment due, of Rs. 1,45,02,546/- 3. Due to the Covid Pandemic Lockdown Situation, the department delay…” Read the full reason“1. We received the Offer Letter from MHADA on 13 August 2020 for our Redevelopment project. 2. On 20th June 2020, we paid our premium instalment due, of Rs. 1,45,02,546/- 3. Due to the Covid Pandemic Lockdown Situation, the department delayed the issue of the receipt of premium instalment Rs. Rs. 1,45,02,546/-, and the receipt was issued to us on 10th May 2022. 4. Due to such COVID delays, the offer letter lapsed. Hence, MHADA asked us to apply for the revised offer letter. MHADA issued a revised offer letter on 10 May 2022. 5. Also, NOC was required to commence construction activities from…”

Source: NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62’s extension records on MahaRERA (P51800014914), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 9 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800014914
Status
Lapsed (registration period ended)
Builder
PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED
Location
Nehru Nagar, Mumbai · 400024
Project type
Residential / Group Housing
Registered on
11 Jan 2018
Completion date at registration
December 2022
Latest completion date
December 2025
Delay so far
36 months
Homes
56
Sold or booked
100%
Towers
1
Complaints on MahaRERA
9
Court cases listed
0
MahaRERA regulatory orders
2
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NEHRU NAGAR SHARADA CHS LTD BLDG NO 62100%100%100%95%

Commencement certificate (CC), as filed on MahaRERA

  • NEHRU NAGAR SHARADA CHS LTD BLDG NO 62: covers 18 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 every month.

NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK60024
1 Room Kitchen25516
1 BHK40016
  • Buildings: NEHRU NAGAR SHARADA CHS LTD BLDG NO 62 (18 floors, 56 units)
  • Car parking: 30 covered, 10 open
  • Land: 1,035 sq m (about 0.3 acres) · sanctioned built-up 2,337 sq m · recreational space 223 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Parsn Construction AND Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 57 months); 6 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 18 complaints on MahaRERA across 3 projects.

Read Google reviews of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62

What is the possession date of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 in Nehru Nagar, Mumbai is 31 December 2025 — 36 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62's builder has filed on MahaRERA, the official one, is 31 December 2025, already 36 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62's builder applied to MahaRERA to extend the completion date 4 times: to 30 December 2023, giving the reason "Explanatory note regarding the state of development works in the projects and reason for not completing the development works in the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making application for the registration of ‘NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62’ – As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 30th DECEMBER 2022 as the project completion date, we will not able to complete the project due to various unavoidable reasons. Such as 1. In 2020 due to the Pandemic situa…"; to 31 December 2024, giving the reason "1. We received the Offer Letter from MHADA on 13 August 2020 for our Redevelopment project. 2. On 20th June 2020, we paid our premium instalment due, of Rs. 1,45,02,546/- 3. Due to the Covid Pandemic Lockdown Situation, the department delayed the issue of the receipt of premium instalment Rs. Rs. 1,45,02,546/-, and the receipt was issued to us on 10th May 2022. 4. Due to such COVID delays, the offer letter lapsed. Hence, MHADA asked us to apply for the revised offer letter. MHADA issued a revised offer letter on 10 May 2022. 5. Also, NOC was required to commence construction activities from…"; to 30 June 2025, giving the reason "OC PENDING. Process under progress."; to 31 December 2025, giving the reason "1. We received the Offer Letter from MHADA on 13 August 2020 for our Redevelopment project. 2. On 20th June 2020, we paid our premium instalment due, of Rs. 1,45,02,546/- 3. Due to the Covid Pandemic Lockdown Situation, the department delayed the issue of the receipt of premium instalment Rs. Rs. 1,45,02,546/-, and the receipt was issued to us on 10th May 2022. 4. Due to such COVID delays, the offer letter lapsed. Hence, MHADA asked us to apply for the revised offer letter. MHADA issued a revised offer letter on 10 May 2022. 5. Also, NOC was required to commence construction activities from…".

What is the RERA number of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 in Nehru Nagar, Mumbai is P51800014914.

Is NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 is registered as P51800014914 and its status is "Lapsed (registration period ended)".

What is the construction status of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NEHRU NAGAR SHARADA CHS LTD BLDG NO 62 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 have complaints on MahaRERA?

9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 is registered on MahaRERA as P51800014914, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 36 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62's possession date changes?

The latest dates are on NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62's MahaRERA page (P51800014914). GharKundli's Kundli Watch sends a free WhatsApp update on NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 have?

According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 has one building filed: NEHRU NAGAR SHARADA CHS LTD BLDG NO 62 with 18 floors and 56 units.

What are the flat sizes (carpet area) in NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62: 2 BHK: 600 sq ft carpet (24 homes); 1 Room Kitchen: 255 sq ft carpet (16 homes); 1 BHK: 400 sq ft carpet (16 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 30 covered and 10 open car parking spaces for NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62.

How big is the land of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 stands on 1,035 sq m of land (about 0.3 acres), with 2,337 sq m of sanctioned built-up area and 223 sq m of recreational open space.

What is the track record of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Construction AND Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 57 months); 6 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 18 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

Google Maps has reviews of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 by PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED is in Nehru Nagar, Mumbai (pincode 400024), near Kurla East, Kurla West, Chembur, Maharashtra, and is registered on MahaRERA as P51800014914, per GharKundli's check of MahaRERA records.

How many homes are in NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 has 56 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 was registered on MahaRERA on 11 January 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

No court cases are listed for NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NEHRU NAGAR SHARADA CHS LTD BLDG NO. 62?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED, which has 4 other projects registered on MahaRERA.

Other projects in pincode 400024

All 85 projects in Kurla East (400024) →

Other projects by PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.