NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5
by PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED · Nehru Nagar, MumbaiAlso near Kurla East, Kurla West, Chembur
Possession date of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5: 31 December 2025, moved from 30 June 2021 (54 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800015096. Status: Lapsed (registration period ended). MahaRERA has issued a regulatory order on this project.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
How the possession date of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51800010074)
Reason the builder gave MahaRERA: “As per Letter Attached.”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51800012537)
Reason the builder gave MahaRERA:
“Explanatory note regarding the state of development works in the projects and reason for not completing the development works in the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the appl…” Read the full reason
“Explanatory note regarding the state of development works in the projects and reason for not completing the development works in the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of ‘NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5’ – As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 31st December 2022 as the project completion date. We will not be able to complete the project due to various unavoidable reasons. Such as a) Implementation of the G…”30 June 2025
Extended at the builder's request (MahaRERA application EXT51800024813)
Reason the builder gave MahaRERA: “Applied for OC. Oc is in progress.”
31 December 2025
Extended at the builder's request (MahaRERA application EA08072502006)
Reason the builder gave MahaRERA:
“Impact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a s…” Read the full reason
“Impact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these mat…”
Source: NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5’s extension records on MahaRERA (P51800015096), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800015096
- Status
- Lapsed (registration period ended)
- Builder
- PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED
- Location
- Nehru Nagar, Mumbai · 400024
- Project type
- Residential / Group Housing
- Registered on
- 24 Jan 2018
- Completion date at registration
- June 2021
- Latest completion date
- December 2025
- Delay so far
- 54 months
- Homes
- 80
- Sold or booked
- 98%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NEHRU NAGAR PANCHRATNA CHS LTD BLDG NO 5 | 100% | 100% | 100% | 95% |
Commencement certificate (CC), as filed on MahaRERA
- NEHRU NAGAR PANCHRATNA CHS LTD BLDG NO 5: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 every month.
NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 393 | 29 |
| 1 Room Kitchen | 255 | 28 |
| 2 BHK | 600 | 23 |
| Office Space | 255 – 2,000 | 4 |
- Buildings: NEHRU NAGAR PANCHRATNA CHS LTD BLDG NO 5 (17 floors, 84 units)
- Car parking: 1 open
- Land: 1,503 sq m (about 0.4 acres)
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Parsn Construction AND Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 57 months); 6 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 18 complaints on MahaRERA across 3 projects.
Read Google reviews of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5
What is the possession date of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 in Nehru Nagar, Mumbai is 31 December 2025 — 54 months later than 30 June 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5's builder has filed on MahaRERA, the official one, is 31 December 2025, already 54 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 extended?
According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5's builder applied to MahaRERA to extend the completion date 4 times: to 30 June 2022, giving the reason "As per Letter Attached."; to 31 December 2024, giving the reason "Explanatory note regarding the state of development works in the projects and reason for not completing the development works in the projects within the period declared in the declaration submitted in FORM ‘B’ at the time of making the application for the registration of ‘NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5’ – As per the details mentioned at the time of registration of the project at the MahaRERA Website we had mentioned 31st December 2022 as the project completion date. We will not be able to complete the project due to various unavoidable reasons. Such as a) Implementation of the G…"; to 30 June 2025, giving the reason "Applied for OC. Oc is in progress."; to 31 December 2025, giving the reason "Impact of Pandemic and Rising Construction Material Costs: The COVID-19 pandemic has had a profound and far-reaching impact on the construction industry, both locally and globally. As a direct consequence of the pandemic, there has been a significant and sustained increase in the prices of essential construction materials, including but not limited to cement, steel, copper, electrical components, plumbing materials, and paints. This escalation in material costs has resulted in severe financial strain, disrupting the supply chain and leading to delays in procurement and delivery of these mat…".
What is the RERA number of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 in Nehru Nagar, Mumbai is P51800015096.
Is NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 is registered as P51800015096 and its status is "Lapsed (registration period ended)".
What is the construction status of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NEHRU NAGAR PANCHRATNA CHS LTD BLDG NO 5 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 is registered on MahaRERA as P51800015096, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5's possession date changes?
The latest dates are on NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5's MahaRERA page (P51800015096). GharKundli's Kundli Watch sends a free WhatsApp update on NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 have?
According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 has one building filed: NEHRU NAGAR PANCHRATNA CHS LTD BLDG NO 5 with 17 floors and 84 units.
What are the flat sizes (carpet area) in NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5: 1 BHK: 393 sq ft carpet (29 homes); 1 Room Kitchen: 255 sq ft carpet (28 homes); 2 BHK: 600 sq ft carpet (23 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 open car parking spaces for NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5.
How big is the land of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 stands on 1,503 sq m of land (about 0.4 acres).
What is the track record of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Construction AND Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 57 months); 6 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 18 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
Google Maps has reviews of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 by PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED is in Nehru Nagar, Mumbai (pincode 400024), near Kurla East, Kurla West, Chembur, Maharashtra, and is registered on MahaRERA as P51800015096, per GharKundli's check of MahaRERA records.
How many homes are in NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 has 80 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.
When was NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 was registered on MahaRERA on 24 January 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
No court cases are listed for NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5 on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of NEHRU NAGAR PANCHRATNA CHS LTD, BLDG. NO.5
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400024
- SAPTARSHI MARK
- VEER SIDDHANAK CHS LTD
- SAPTARSHI AVALON
- AMBARISH CHS LTD
- RAGHAV PARIJAT
- Ruparel Crest
- SAYBA TULIP
- DTG APEX
Other projects by PARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.