by Integrated Spaces Limited · Andheri West, Mumbai 400058Also near Andheri Railway Station, Vesava, Andheri East

What’s in the report? →

Possession date of Integrated Kavya (MahaRERA P51800052486): 30 October 2027. It has 28 homes (2 BHK and 3 BHK, 713–1180 sq ft carpet), 5% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800052486, and currently active. Its completion date is now October 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: MahaRERA website — records for P51800052486, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Integrated Kavya?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Integrated Kavya has moved

  1. 30 June 2027

    Completion date given when the project was registered

  2. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Integrated Kavya’s extension records on MahaRERA (P51800052486), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Integrated Kavya

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800052486
Status
Registered and active
Builder
Integrated Spaces Limited
Location
Andheri West, Mumbai · 400058
Project type
Others
Registered on
8 Sep 2023
Completion date at registration
June 2027
Latest completion date
October 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
28
Sold or booked
5%
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Integrated Kavya, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
A Wing100%66.67%22.5%0%
B Wing100%60%21.25%0%

Commencement certificate (CC), as filed on MahaRERA

  • A Wing: covers Wing ‘A’ up to top of 10th floor & Wing ‘B’ up to top of 10th floor
  • B Wing: covers Wing ‘A’ up to top of 10th floor & Wing ‘B’ up to top of 10th floor

Latest CC order on MahaRERA: dated 21/11/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Integrated Kavya every 1–2 months.

Integrated Kavya: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK812 – 1,04022
Other1,047 – 1,1805
2 BHK7131
  • Buildings: A Wing (11 floors, 16 units) · B Wing (11 floors, 12 units)
  • Land: 3,078 sq m (about 0.8 acres) · sanctioned built-up 3,946 sq m
  • Land, as filed: 638/1
  • Map: Get directions

The builder’s record and reviews

Integrated Spaces (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 30 months); 5 still being built, 1 past the promised date (typically 87 months late); 2 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Integrated Kavya →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Integrated Kavya: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Integrated Kavya

What is the possession date of Integrated Kavya?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Integrated Kavya in Andheri West, Mumbai is 30 October 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Integrated Kavya?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Integrated Kavya's builder has filed on MahaRERA, the official one, is 30 October 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Integrated Kavya?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Integrated Kavya in Andheri West, Mumbai is P51800052486.

Is Integrated Kavya registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Kavya is registered as P51800052486 and its status is "Registered and active".

What is the current construction status of Integrated Kavya? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Kavya's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 60% to 66.67% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Integrated Kavya have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Integrated Kavya safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Kavya is registered on MahaRERA as P51800052486, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Integrated Kavya?

Integrated Kavya is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Flats in Integrated Kavya start at 713 sq ft carpet, above that limit, so expect 5%. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Integrated Kavya?

For a flat in Integrated Kavya (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Integrated Kavya received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Kavya is still under construction, with 30 October 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Is Integrated Kavya a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Kavya is a redevelopment: 9 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.

Has Integrated Kavya uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Integrated Kavya was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Integrated Kavya's possession date changes?

The latest dates are on Integrated Kavya's MahaRERA page (P51800052486). GharKundli's Kundli Watch sends a free WhatsApp update on Integrated Kavya every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Integrated Kavya have?

According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Kavya has 2 buildings filed: A Wing with 11 floors and 16 units; B Wing with 11 floors and 12 units.

What are the flat sizes (carpet area) in Integrated Kavya?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Integrated Kavya: 3 BHK: 812 to 1040 sq ft carpet (22 homes); Other: 1047 to 1180 sq ft carpet (5 homes); 2 BHK: 713 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Integrated Kavya?

According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Kavya stands on 3,078 sq m of land (about 0.8 acres), with 3,946 sq m of sanctioned built-up area.

What is the track record of Integrated Kavya's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Spaces (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 30 months); 5 still being built, 1 past the promised date (typically 87 months late); 2 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Integrated Kavya?

Google Maps has reviews of Integrated Kavya written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Integrated Kavya?

Integrated Kavya by Integrated Spaces Limited is in Andheri West, Mumbai, pincode 400058 (near Andheri Railway Station, Vesava, Andheri East), Maharashtra, and is registered on MahaRERA as P51800052486, per GharKundli's check of MahaRERA records. Its land is filed as 638/1. GharKundli lists all 148 MahaRERA projects in Andheri West (400058).

How many flats are in Integrated Kavya, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Kavya has 28 homes in 2 towers registered on MahaRERA, and 5% of them are sold or booked.

When was Integrated Kavya registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Kavya was registered on MahaRERA on 8 September 2023. GharKundli did not find a title report on the land on file there.

Does Integrated Kavya have any legal issues or court cases?

No court cases are listed for Integrated Kavya on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Integrated Kavya?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Integrated Spaces Limited, which has 5 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in Andheri West (400058)

All 148 projects in Andheri West (400058) →

Other projects by Integrated Spaces Limited

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.