Integrated Arya
by Integrated Spaces Limited · Narayan Nagar, Ghatkopar West, MumbaiAlso near Rajawadi, Barve Nagar
Possession date of Integrated Arya: 30 April 2029, moved from 31 March 2019 (117 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800004521, and currently active. Its completion date has moved from March 2019 to April 2029: 117 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Integrated Arya?
How the possession date of Integrated Arya has moved
31 March 2019
Completion date given when the project was registered
31 December 2020
Extended at the builder's request (MahaRERA application EXT51800000665)
Reason the builder gave MahaRERA: ““In the present litigation we are at Consent term stage also awaiting DP 2034 for further approvals. ””
31 December 2020
Extended at the builder's request (MahaRERA application EXT51800005822)
Reason the builder gave MahaRERA:
“Due to adverse market condition and slowdown in Real Estate Industry in 2019, there has been a delay in completion of balance construction and finishing work at site. Hence we seek further extension of 9 months to complete work and obtain O…” Read the full reason
“Due to adverse market condition and slowdown in Real Estate Industry in 2019, there has been a delay in completion of balance construction and finishing work at site. Hence we seek further extension of 9 months to complete work and obtain Occupation Certificate for the project.”31 March 2022
Extended at the builder's request (MahaRERA application EXT51800011041)
Reason the builder gave MahaRERA:
“Flooring, Tiling work, Electrification work, Internal and external plumbing work has been completed of Wing A & B and initiate same work in wing C,D,E,F. Due to COVID 19 lockdown, there has been delay in completion of finishing work at site…” Read the full reason
“Flooring, Tiling work, Electrification work, Internal and external plumbing work has been completed of Wing A & B and initiate same work in wing C,D,E,F. Due to COVID 19 lockdown, there has been delay in completion of finishing work at site. Hence, we seek further extension of 3 months i.e. upto 31.03.2022.”31 July 2022
Extended at the builder's request (MahaRERA application EXT51800011566)
Reason the builder gave MahaRERA:
“Project is ready for application for OC we have completed 12 compliance out of 13 compliance for application of OC and we will apply for OC on or before 31-03-2022. For completion of balance finishing work and to take water connection at si…” Read the full reason
“Project is ready for application for OC we have completed 12 compliance out of 13 compliance for application of OC and we will apply for OC on or before 31-03-2022. For completion of balance finishing work and to take water connection at site, we seek further extension of 4 months i.e. upto 31-07-2022 to complete ancillary work for delivery of project.”30 April 2025
Extended at the builder's request (MahaRERA application EXT51800013666)
Reason the builder gave MahaRERA:
“1 Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis 2 Lack of manpower and labour supply post covid time. Most of the North Indian labourers were away and hence we had a v…” Read the full reason
“1 Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis 2 Lack of manpower and labour supply post covid time. Most of the North Indian labourers were away and hence we had a very bad time to re establish the work momentum. 3 Unseasonal and heavy rain during odd months also impacted badly in our project construction phase 4 The sales in the market was absolutely bad and hence we could not get enough business and fresh income to run the construction flow as per the schedule 5 Most of our investors and directors faced issues in f…”31 December 2028
Extended at the builder's request (MahaRERA application EXT51800025075)
Reason the builder gave MahaRERA:
“We "Integrated Spaces Limited", promoters of the project named "Integrated Arya" located at CTS No. 183C/1 and 183C/2 of Village Kirol, Taluka Kurla, District Mumbai Suburhan, 400086 The project consists of total 6 wings and cach wing consi…” Read the full reason
“We "Integrated Spaces Limited", promoters of the project named "Integrated Arya" located at CTS No. 183C/1 and 183C/2 of Village Kirol, Taluka Kurla, District Mumbai Suburhan, 400086 The project consists of total 6 wings and cach wing consist of ground plus & floors. Plinth Approval was received for the project in the year 8 July 2015 and Full CC (G+7) for the project was received on 6th May 2019 We have completed ground plus 7 floors as per the approval received also we have obtained part occupation certificate for ground plus 7 floors dated May 2022. Out of 102 units (including 8ª floor u…”30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Integrated Arya’s extension records on MahaRERA (P51800004521), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Integrated Arya
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 2 court cases, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800004521
- Status
- Registered and active
- Builder
- Integrated Spaces Limited
- Location
- Narayan Nagar, Ghatkopar West, Mumbai · 400086
- Project type
- Others
- Registered on
- 9 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- April 2029
- Delay so far
- 117 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 159
- Sold or booked
- 80%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of Integrated Arya, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| INTEGRATED ARYA | 100% | 88% | 85% | 92% |
Commencement certificate (CC), as filed on MahaRERA
- INTEGRATED ARYA: covers C.C. as per approved amended plans dtd. 08.04.2019
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Integrated Arya every month.
Integrated Arya: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 345 – 477 | 125 |
| 2 BHK | 614 – 615 | 31 |
| Shops | 181 – 309 | 8 |
| 1 Room Kitchen | 338 – 345 | 3 |
- Buildings: INTEGRATED ARYA (11 floors, 167 units)
- Land: 3,252 sq m (about 0.8 acres) · sanctioned built-up 6,891 sq m · recreational space 488 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Integrated Spaces (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 30 months); 5 still being built, 1 past the promised date (typically 87 months late); 2 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Integrated Arya →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Integrated Arya: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Integrated Arya
What is the possession date of Integrated Arya?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Integrated Arya in Narayan Nagar, Ghatkopar West, Mumbai is 30 April 2029 — 117 months later than 31 March 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Integrated Arya?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Integrated Arya's builder has filed on MahaRERA, the official one, is 30 April 2029, already 117 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Integrated Arya extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Arya's builder applied to MahaRERA to extend the completion date 6 times: to 31 December 2020, giving the reason "“In the present litigation we are at Consent term stage also awaiting DP 2034 for further approvals. ”"; to 31 December 2020, giving the reason "Due to adverse market condition and slowdown in Real Estate Industry in 2019, there has been a delay in completion of balance construction and finishing work at site. Hence we seek further extension of 9 months to complete work and obtain Occupation Certificate for the project."; to 31 March 2022, giving the reason "Flooring, Tiling work, Electrification work, Internal and external plumbing work has been completed of Wing A & B and initiate same work in wing C,D,E,F. Due to COVID 19 lockdown, there has been delay in completion of finishing work at site. Hence, we seek further extension of 3 months i.e. upto 31.03.2022."; to 31 July 2022, giving the reason "Project is ready for application for OC we have completed 12 compliance out of 13 compliance for application of OC and we will apply for OC on or before 31-03-2022. For completion of balance finishing work and to take water connection at site, we seek further extension of 4 months i.e. upto 31-07-2022 to complete ancillary work for delivery of project."; to 30 April 2025, giving the reason "1 Due to COVID-19 pandemic, the regular flow of work is hampered on account of unavailability of labour on regular basis 2 Lack of manpower and labour supply post covid time. Most of the North Indian labourers were away and hence we had a very bad time to re establish the work momentum. 3 Unseasonal and heavy rain during odd months also impacted badly in our project construction phase 4 The sales in the market was absolutely bad and hence we could not get enough business and fresh income to run the construction flow as per the schedule 5 Most of our investors and directors faced issues in f…"; to 31 December 2028, giving the reason "We "Integrated Spaces Limited", promoters of the project named "Integrated Arya" located at CTS No. 183C/1 and 183C/2 of Village Kirol, Taluka Kurla, District Mumbai Suburhan, 400086 The project consists of total 6 wings and cach wing consist of ground plus & floors. Plinth Approval was received for the project in the year 8 July 2015 and Full CC (G+7) for the project was received on 6th May 2019 We have completed ground plus 7 floors as per the approval received also we have obtained part occupation certificate for ground plus 7 floors dated May 2022. Out of 102 units (including 8ª floor u…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Integrated Arya?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Integrated Arya in Narayan Nagar, Ghatkopar West, Mumbai is P51800004521.
Is Integrated Arya registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Arya is registered as P51800004521 and its status is "Registered and active".
What is the construction status of Integrated Arya?
According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Arya's status on MahaRERA is "Registered and active". As filed by the builder, slab work on INTEGRATED ARYA is 88% done and internal work 85%. GharKundli's full report compares construction progress with the deadline.
Does Integrated Arya have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Integrated Arya safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Arya is registered on MahaRERA as P51800004521, its completion date has moved 117 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Integrated Arya's possession date changes?
The latest dates are on Integrated Arya's MahaRERA page (P51800004521). GharKundli's Kundli Watch sends a free WhatsApp update on Integrated Arya every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Integrated Arya have?
According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Arya has one building filed: INTEGRATED ARYA with 11 floors and 167 units.
What are the flat sizes (carpet area) in Integrated Arya?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Integrated Arya: 1 BHK: 345 to 477 sq ft carpet (125 homes); 2 BHK: 614 to 615 sq ft carpet (31 homes); 1 Room Kitchen: 338 to 345 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Integrated Arya?
According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Arya stands on 3,252 sq m of land (about 0.8 acres), with 6,891 sq m of sanctioned built-up area and 488 sq m of recreational open space.
What is the track record of Integrated Arya's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Spaces (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 30 months); 5 still being built, 1 past the promised date (typically 87 months late); 2 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Integrated Arya?
Google Maps has reviews of Integrated Arya written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Integrated Arya?
Integrated Arya by Integrated Spaces Limited is in Narayan Nagar, Ghatkopar West, Mumbai (pincode 400086), near Rajawadi, Barve Nagar, Maharashtra, and is registered on MahaRERA as P51800004521, per GharKundli's check of MahaRERA records.
How many homes are in Integrated Arya?
According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Arya has 159 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.
When was Integrated Arya registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Integrated Arya was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Integrated Arya?
2 court cases are listed for Integrated Arya on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Integrated Arya?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Integrated Spaces Limited, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Integrated Arya
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Mumbai Suburban →
Other projects in pincode 400086
- ASHOK ODYSSEY - A WING
- Elanza Commercial
- Tivon Park Wing E and F
- Kadri Residency
- Crystal Palladian 207
- 72 WEST
- Neelyog Regent
- Redevlopement of SBI Madhur Milan CHSL
Other projects by Integrated Spaces Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.