Suburban Irasa Greens

by SUBURBAN SPACES LLP · Village Dohole, Thane 421302Registered on MahaRERA as “Irasa Greens”

What’s in the report? →

Possession date of Suburban Irasa Greens (MahaRERA P51700005934): 30 April 2028, moved from 30 December 2023 (48 months later). It has 176 homes, 16% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700005934, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700005934, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Suburban Irasa Greens?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Suburban Irasa Greens has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT51700019082)

    Reason the builder gave MahaRERA: “Due to unavoidable circumstances, promoter was not unable to complete project in time hence wants extension.”
  3. 31 December 2027

    Extended at the builder's request (MahaRERA application EA29042620772)

    Reason the builder gave MahaRERA:
    “• The completion of the project has been delayed due to circumstances beyond the control of the promoter. The construction activities were affected by delays in approvals from concerned authorities, shortage of skilled manpower, and intermi…” Read the full reason“• The completion of the project has been delayed due to circumstances beyond the control of the promoter. The construction activities were affected by delays in approvals from concerned authorities, shortage of skilled manpower, and intermittent disruption in the supply of construction materials. Despite best efforts made by the promoter to adhere to the original timeline, these unforeseen factors have impacted the progress of the project. • The promoter is committed to completing the project at the earliest with maintained quality standards and therefore seeks an extension of the project c…”
  4. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Suburban Irasa Greens’s extension records on MahaRERA (P51700005934), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Suburban Irasa Greens

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700005934
Status
Registered and active
Builder
SUBURBAN SPACES LLP
Location
Village Dohole, Thane · 421302
Project type
Others
Registered on
14 Aug 2017
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
176
Sold or booked
16%
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Suburban Irasa Greens, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
3100%100%80%0%
20%0%0%0%
1100%20%0%0%
40%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • 3: covers 5 floors
  • 2: covers 5 floors
  • 1: covers 5 floors
  • 4: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Suburban Irasa Greens every 1–2 months.

Suburban Irasa Greens: buildings, flats and land, as filed on MahaRERA

  • Buildings: 3 (5 floors, 60 units) · 2 (5 floors, 40 units) · 1 (5 floors, 40 units) · 4 (5 floors, 47 units)
  • Car parking: 8 open
  • Land: 9,300 sq m (about 2.3 acres) · sanctioned built-up 6,979 sq m · recreational space 1,069 sq m
  • Land, as filed: Survey No 124 Hissa No 3A Survey No 124 Hissa No 3B Survey No 125 Hissa No 1P
  • Map: Get directions

The builder’s record and reviews

Suburban Spaces has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 still being built, 2 past the promised date (typically 26 months late); 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Suburban Irasa Greens →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Suburban Irasa Greens: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Suburban Irasa Greens

What is the possession date of Suburban Irasa Greens?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Suburban Irasa Greens in Village Dohole, Thane is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

The date has already moved 48 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Suburban Irasa Greens?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Suburban Irasa Greens's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Suburban Irasa Greens extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Suburban Irasa Greens's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "Due to unavoidable circumstances, promoter was not unable to complete project in time hence wants extension."; to 31 December 2027, giving the reason "• The completion of the project has been delayed due to circumstances beyond the control of the promoter. The construction activities were affected by delays in approvals from concerned authorities, shortage of skilled manpower, and intermittent disruption in the supply of construction materials. Despite best efforts made by the promoter to adhere to the original timeline, these unforeseen factors have impacted the progress of the project. • The promoter is committed to completing the project at the earliest with maintained quality standards and therefore seeks an extension of the project c…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Suburban Irasa Greens?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Suburban Irasa Greens in Village Dohole, Thane is P51700005934.

Is Suburban Irasa Greens registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Suburban Irasa Greens is registered as P51700005934 and its status is "Registered and active".

What is the current construction status of Suburban Irasa Greens? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Suburban Irasa Greens's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Suburban Irasa Greens have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Suburban Irasa Greens safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Suburban Irasa Greens is registered on MahaRERA as P51700005934, its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Suburban Irasa Greens?

Suburban Irasa Greens is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Suburban Irasa Greens?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Suburban Irasa Greens: gharkundli.com/tools/property-cost-calculator

Has Suburban Irasa Greens received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Suburban Irasa Greens is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Suburban Irasa Greens uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Suburban Irasa Greens was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Suburban Irasa Greens's possession date changes?

The latest dates are on Suburban Irasa Greens's MahaRERA page (P51700005934). GharKundli's Kundli Watch sends a free WhatsApp update on Suburban Irasa Greens every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Suburban Irasa Greens have?

According to GharKundli's check of MahaRERA records (updated October 2026), Suburban Irasa Greens has 4 buildings filed: 3 with 5 floors and 60 units; 2 with 5 floors and 40 units; 1 with 5 floors and 40 units; 4 with 5 floors and 47 units.

How much parking does Suburban Irasa Greens have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 8 open car parking spaces for Suburban Irasa Greens.

How big is the land of Suburban Irasa Greens?

According to GharKundli's check of MahaRERA records (updated October 2026), Suburban Irasa Greens stands on 9,300 sq m of land (about 2.3 acres), with 6,979 sq m of sanctioned built-up area and 1,069 sq m of recreational open space.

What is the track record of Suburban Irasa Greens's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Suburban Spaces has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 2 still being built, 2 past the promised date (typically 26 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Suburban Irasa Greens?

Google Maps has reviews of Suburban Irasa Greens written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Suburban Irasa Greens?

Suburban Irasa Greens by SUBURBAN SPACES LLP is in Village Dohole, Thane, pincode 421302, Maharashtra, and is registered on MahaRERA as P51700005934, per GharKundli's check of MahaRERA records. Its land is filed as Survey No 124 Hissa No 3A Survey No 124 Hissa No 3B Survey No 125 Hissa No 1P. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Suburban Irasa Greens, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Suburban Irasa Greens has 176 homes in 4 towers registered on MahaRERA, and 16% of them are sold or booked.

When was Suburban Irasa Greens registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Suburban Irasa Greens was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Does Suburban Irasa Greens have any legal issues or court cases?

No court cases are listed for Suburban Irasa Greens on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Suburban Irasa Greens?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUBURBAN SPACES LLP, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2028 in Thane →

Other projects in Bhiwandi

All 382 projects in Bhiwandi (421302) →

Other projects by SUBURBAN SPACES LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.