Possession date of PEHLA GHAR - DIVEKAR COMPLEX: 31 December 2026, moved from 30 December 2023 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700004024, and currently active. 4 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about PEHLA GHAR - DIVEKAR COMPLEX?
How the possession date of PEHLA GHAR - DIVEKAR COMPLEX has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51700018522)
Reason the builder gave MahaRERA: “Application under section 6 for extension for want of completing OC formalities and finishing the building”
31 December 2025
Extended at the builder's request (MahaRERA application EA28052501270)
Reason the builder gave MahaRERA:
“We have submitted an application (RERA Number P517O0004024) for the extension of our registration with MAHA RERA, in accordance with the provisions outlined in Section 7(3) of the RERA Act, requesting an extension for a duration of 31-12-20…” Read the full reason
“We have submitted an application (RERA Number P517O0004024) for the extension of our registration with MAHA RERA, in accordance with the provisions outlined in Section 7(3) of the RERA Act, requesting an extension for a duration of 31-12-2025 months. The project has encountered several challenges that have necessitated a revision of our original timeline. This application is made with the intent of extending the registration's validity with MAHA RERA, taking into consideration the best interests of a significant number of allottees involved in the project. Section 7(3) of the RERA Act has g…”31 December 2026
Extended at the builder's request (MahaRERA application EA30012619654)
Reason the builder gave MahaRERA:
“We have submitted an application (RERA Number P51700004024) for the extension of our registration with MAHA RERA, in accordance with the provisions outlined in Section 7(3) of the RERA Act, requesting an extension for a duration of 31-12-20…” Read the full reason
“We have submitted an application (RERA Number P51700004024) for the extension of our registration with MAHA RERA, in accordance with the provisions outlined in Section 7(3) of the RERA Act, requesting an extension for a duration of 31-12-2026 months. The project has encountered several challenges that have necessitated a revision of our original timeline. This application is made with the intent of extending the registration's validity with MAHA RERA, taking into consideration the best interests of a significant number of allottees involved in the project.Section 7(3) of the RERA Act has gi…”
Source: PEHLA GHAR - DIVEKAR COMPLEX’s extension records on MahaRERA (P51700004024), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on PEHLA GHAR - DIVEKAR COMPLEX
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 4 complaints, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700004024
- Status
- Registered and active
- Builder
- LAABH BUILDCON
- Location
- Sai Baba Temple, Thane · 421302
- Project type
- Others
- Registered on
- 7 Aug 2017
- Completion date at registration
- December 2023
- Latest completion date
- December 2026
- Delay so far
- 36 months
- Homes
- 175
- Sold or booked
- 58%
- Towers
- 3
- Complaints on MahaRERA
- 4
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of PEHLA GHAR - DIVEKAR COMPLEX, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BLDG A | 100% | 100% | 100% | 90% |
| BLDG B | 100% | 100% | 100% | 90% |
| BLDG C | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- BLDG A: covers Ground + 9 Floor
- BLDG B: covers Ground + 9 Floor
- BLDG C: covers Ground + 8 Floor
Want to know when this changes? Kundli Watch sends a free WhatsApp update on PEHLA GHAR - DIVEKAR COMPLEX every month.
PEHLA GHAR - DIVEKAR COMPLEX: buildings, flats and land, as filed on MahaRERA
- Buildings: BLDG A (9 floors, 66 units) · BLDG B (9 floors, 64 units) · BLDG C (8 floors, 47 units)
- Land: 3,470 sq m (about 0.9 acres) · sanctioned built-up 5,183 sq m · recreational space 631 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Laabh Builders And Developers (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 22 months late); 2 lapsed. 7 complaints on MahaRERA across 3 projects.
Read Google reviews of PEHLA GHAR - DIVEKAR COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
PEHLA GHAR - DIVEKAR COMPLEX: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about PEHLA GHAR - DIVEKAR COMPLEX
What is the possession date of PEHLA GHAR - DIVEKAR COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for PEHLA GHAR - DIVEKAR COMPLEX in Sai Baba Temple, Thane is 31 December 2026 — 36 months later than 30 December 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for PEHLA GHAR - DIVEKAR COMPLEX?
Builders and listing sites often quote an earlier "target" date for handover. The completion date PEHLA GHAR - DIVEKAR COMPLEX's builder has filed on MahaRERA, the official one, is 31 December 2026, already 36 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of PEHLA GHAR - DIVEKAR COMPLEX extended?
According to GharKundli's check of MahaRERA records (updated October 2026), PEHLA GHAR - DIVEKAR COMPLEX's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "Application under section 6 for extension for want of completing OC formalities and finishing the building"; to 31 December 2025, giving the reason "We have submitted an application (RERA Number P517O0004024) for the extension of our registration with MAHA RERA, in accordance with the provisions outlined in Section 7(3) of the RERA Act, requesting an extension for a duration of 31-12-2025 months. The project has encountered several challenges that have necessitated a revision of our original timeline. This application is made with the intent of extending the registration's validity with MAHA RERA, taking into consideration the best interests of a significant number of allottees involved in the project. Section 7(3) of the RERA Act has g…"; to 31 December 2026, giving the reason "We have submitted an application (RERA Number P51700004024) for the extension of our registration with MAHA RERA, in accordance with the provisions outlined in Section 7(3) of the RERA Act, requesting an extension for a duration of 31-12-2026 months. The project has encountered several challenges that have necessitated a revision of our original timeline. This application is made with the intent of extending the registration's validity with MAHA RERA, taking into consideration the best interests of a significant number of allottees involved in the project.Section 7(3) of the RERA Act has gi…".
What is the RERA number of PEHLA GHAR - DIVEKAR COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of PEHLA GHAR - DIVEKAR COMPLEX in Sai Baba Temple, Thane is P51700004024.
Is PEHLA GHAR - DIVEKAR COMPLEX registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PEHLA GHAR - DIVEKAR COMPLEX is registered as P51700004024 and its status is "Registered and active".
What is the construction status of PEHLA GHAR - DIVEKAR COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), PEHLA GHAR - DIVEKAR COMPLEX's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does PEHLA GHAR - DIVEKAR COMPLEX have complaints on MahaRERA?
4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is PEHLA GHAR - DIVEKAR COMPLEX safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), PEHLA GHAR - DIVEKAR COMPLEX is registered on MahaRERA as P51700004024, its completion date has moved 36 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if PEHLA GHAR - DIVEKAR COMPLEX's possession date changes?
The latest dates are on PEHLA GHAR - DIVEKAR COMPLEX's MahaRERA page (P51700004024). GharKundli's Kundli Watch sends a free WhatsApp update on PEHLA GHAR - DIVEKAR COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does PEHLA GHAR - DIVEKAR COMPLEX have?
According to GharKundli's check of MahaRERA records (updated October 2026), PEHLA GHAR - DIVEKAR COMPLEX has 3 buildings filed: BLDG A with 9 floors and 66 units; BLDG B with 9 floors and 64 units; BLDG C with 8 floors and 47 units.
How big is the land of PEHLA GHAR - DIVEKAR COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), PEHLA GHAR - DIVEKAR COMPLEX stands on 3,470 sq m of land (about 0.9 acres), with 5,183 sq m of sanctioned built-up area and 631 sq m of recreational open space.
What is the track record of PEHLA GHAR - DIVEKAR COMPLEX's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Laabh Builders And Developers (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 22 months late); 2 lapsed. 7 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of PEHLA GHAR - DIVEKAR COMPLEX?
Google Maps has reviews of PEHLA GHAR - DIVEKAR COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is PEHLA GHAR - DIVEKAR COMPLEX?
PEHLA GHAR - DIVEKAR COMPLEX by LAABH BUILDCON is in Sai Baba Temple, Thane (pincode 421302), Maharashtra, and is registered on MahaRERA as P51700004024, per GharKundli's check of MahaRERA records.
How many homes are in PEHLA GHAR - DIVEKAR COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), PEHLA GHAR - DIVEKAR COMPLEX has 175 homes in 3 towers registered on MahaRERA, and 58% of them are sold or booked.
When was PEHLA GHAR - DIVEKAR COMPLEX registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), PEHLA GHAR - DIVEKAR COMPLEX was registered on MahaRERA on 7 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on PEHLA GHAR - DIVEKAR COMPLEX?
No court cases are listed for PEHLA GHAR - DIVEKAR COMPLEX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of PEHLA GHAR - DIVEKAR COMPLEX?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is LAABH BUILDCON.
Check it yourself on MahaRERA
- How to check the possession date of PEHLA GHAR - DIVEKAR COMPLEX
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Bhiwandi
- ASHOKA COMPLEX
- KOHINOOR UPTOWN T1 & T6
- SAI DEEP RESIDENCY
- REGAL SQUARE PH 4 TOWER 6 AND 8
- NEELKANTH SADAN
- THE PALLAZO
- ARIHANT CITY PHASE-II - K BUILDING
- ROYAL PARK
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.