Ornate Kallisto Phase I
by Ornate Buildcon Developers · Temghar Bhiwandi, Thane
Possession: Ornate Kallisto Phase I is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700011610. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Ornate Kallisto Phase I?
How the possession date of Ornate Kallisto Phase I has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51700003686)
Reason the builder gave MahaRERA:
“due to delay in obtaining permission from the competent authority the project was not been able to be completed on time however we shall complete the project in a span of 1 year from now onwards. the project is almost on the verge of comple…” Read the full reason
“due to delay in obtaining permission from the competent authority the project was not been able to be completed on time however we shall complete the project in a span of 1 year from now onwards. the project is almost on the verge of completion. we request you to grant us the certificate at the earliest.”30 December 2021
Revised completion date on MahaRERA
Source: Ornate Kallisto Phase I’s extension records on MahaRERA (P51700011610), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ornate Kallisto Phase I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Ornate Kallisto Phase IIP51700018908 · possession 30 Dec 2024
- Ornate Kallisto Phase IVP51700033627 · possession 30 Dec 2024
- MahaRERA registration
- P51700011610
- Status
- Completed
- Builder
- Ornate Buildcon Developers
- Location
- Temghar Bhiwandi, Thane · 421302
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2021
- Delay so far
- 24 months
- Homes
- 146
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Ornate Kallisto Phase I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Ornate Kallisto | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ornate Kallisto Phase I every month.
Ornate Kallisto Phase I: buildings, flats and land, as filed on MahaRERA
- Buildings: Ornate Kallisto (12 floors)
- Land: 630 sq m (about 0.2 acres) · sanctioned built-up 4,609 sq m · recreational space 817 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Ornate Buildcon Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 17 months); 4 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Ornate Kallisto Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ornate Kallisto Phase I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Ornate Kallisto Phase I
What is the possession date of Ornate Kallisto Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Ornate Kallisto Phase I in Temghar Bhiwandi, Thane is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Ornate Kallisto Phase I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ornate Kallisto Phase I's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Ornate Kallisto Phase I extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Ornate Kallisto Phase I's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "due to delay in obtaining permission from the competent authority the project was not been able to be completed on time however we shall complete the project in a span of 1 year from now onwards. the project is almost on the verge of completion. we request you to grant us the certificate at the earliest.".
What is the RERA number of Ornate Kallisto Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Ornate Kallisto Phase I in Temghar Bhiwandi, Thane is P51700011610.
Is Ornate Kallisto Phase I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Ornate Kallisto Phase I is registered as P51700011610 and its status is "Completed".
What is the construction status of Ornate Kallisto Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Ornate Kallisto Phase I's status on MahaRERA is "Completed". As filed by the builder, slab work on Ornate Kallisto is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Ornate Kallisto Phase I have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Ornate Kallisto Phase I safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Ornate Kallisto Phase I is registered on MahaRERA as P51700011610, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Ornate Kallisto Phase I have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: Ornate Kallisto Phase II (P51700018908, possession 30 Dec 2024); Ornate Kallisto Phase IV (P51700033627, possession 30 Dec 2024). Check that your agreement names the registration of your own wing.
How can I get updates if Ornate Kallisto Phase I's possession date changes?
The latest dates are on Ornate Kallisto Phase I's MahaRERA page (P51700011610). GharKundli's Kundli Watch sends a free WhatsApp update on Ornate Kallisto Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ornate Kallisto Phase I have?
According to GharKundli's check of MahaRERA records (updated November 2026), Ornate Kallisto Phase I has one building filed: Ornate Kallisto with 12 floors.
How big is the land of Ornate Kallisto Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Ornate Kallisto Phase I stands on 630 sq m of land (about 0.2 acres), with 4,609 sq m of sanctioned built-up area and 817 sq m of recreational open space.
What is the track record of Ornate Kallisto Phase I's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Ornate Buildcon Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 17 months); 4 still being built, none past the promised date yet. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Ornate Kallisto Phase I?
Google Maps has reviews of Ornate Kallisto Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Ornate Kallisto Phase I?
Ornate Kallisto Phase I by Ornate Buildcon Developers is in Temghar Bhiwandi, Thane (pincode 421302), Maharashtra, and is registered on MahaRERA as P51700011610, per GharKundli's check of MahaRERA records.
How many homes are in Ornate Kallisto Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), Ornate Kallisto Phase I has 146 homes in 1 tower registered on MahaRERA.
When was Ornate Kallisto Phase I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Ornate Kallisto Phase I was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Ornate Kallisto Phase I?
No court cases are listed for Ornate Kallisto Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Ornate Kallisto Phase I?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Ornate Buildcon Developers, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Ornate Kallisto Phase I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Bhiwandi
- ASHOKA COMPLEX
- KOHINOOR UPTOWN T1 & T6
- SAI DEEP RESIDENCY
- REGAL SQUARE PH 4 TOWER 6 AND 8
- NEELKANTH SADAN
- THE PALLAZO
- ARIHANT CITY PHASE-II - K BUILDING
- ROYAL PARK
Other projects by Ornate Buildcon Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.