Possession date of Salasar Mahavir Residency (MahaRERA P51700012556): 4 October 2026, moved from 30 December 2021 (54 months later), and it has already passed. It has 44 homes, 48% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700012556. Status: Lapsed (registration period ended). Its completion date has moved from December 2021 to October 2026: 54 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51700012556, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about Salasar Mahavir Residency?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Salasar Mahavir Residency has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 29 December 2022

    Extended at the builder's request (MahaRERA application EXT51700011183)

    Reason the builder gave MahaRERA: “Project delayed due to covid situation.”
  3. 29 December 2023

    Extended at the builder's request (MahaRERA application EXT51700015166)

    Reason the builder gave MahaRERA: “1. Project delayed due to covid situation”
  4. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT51700019613)

    Reason the builder gave MahaRERA:
    “The building has completed in respect to all the construction activity and finishing work. Since the project has got the CRZ NOC in 2013, but due to change in alignment of CRZ line - 2019 changed as per the CRZ notification dated 25/08/2023…” Read the full reason“The building has completed in respect to all the construction activity and finishing work. Since the project has got the CRZ NOC in 2013, but due to change in alignment of CRZ line - 2019 changed as per the CRZ notification dated 25/08/2023, the clearance is yet to receive from the MCZMA Department, due to which our Occupation Certificate process is not able to proceed further.”
  5. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51700027600)

    Reason the builder gave MahaRERA:
    “The building has completed in respect to all the construction activity and finishing work. We have already submitted Architect Certificate for 100% completion of project. The reason behind delay of Occupancy Certificate is that the project…” Read the full reason“The building has completed in respect to all the construction activity and finishing work. We have already submitted Architect Certificate for 100% completion of project. The reason behind delay of Occupancy Certificate is that the project has got the CRZ NOC in 2013, but due to change in alignment of CRZ line - 2019 changed as per the CRZ notification dated 25/08/2023, the clearance is yet to receive from the MCZMA Department, due to which our Occupancy Certificate process is not able to proceed further. Bhiwandi Nizampur City Municipal Corporation also wrote a letter to MCZMA that in resp…”
  6. 4 June 2026

    Extended at the builder's request (MahaRERA application EA12022619803)

    Reason the builder gave MahaRERA:
    “We, Shree Salasar Realty, the promoter of project “Mahavir Residency” having MahaRERA Registration No. P51700012556, hereby declare and confirm that there is no correction or change required in any of the project details submitted and avail…” Read the full reason“We, Shree Salasar Realty, the promoter of project “Mahavir Residency” having MahaRERA Registration No. P51700012556, hereby declare and confirm that there is no correction or change required in any of the project details submitted and available on the MahaRERA portal in respect of this project. We further request the Hon'ble Authority to kindly grant an extension of the MahaRERA Project Registration up to 4th June 2026, being the date of issuance of the Occupancy Certificate (OC) for the said project. Thanking You”
  7. 4 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Salasar Mahavir Residency’s extension records on MahaRERA (P51700012556), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Salasar Mahavir Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700012556
Status
Lapsed (registration period ended)
Builder
SHREE SALASAR REALTY
Location
Adarsh Park, Thane · 421302
Project type
Residential / Group Housing
Registered on
4 Sep 2017
Completion date at registration
December 2021
Latest completion date
October 2026
Delay so far
54 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
44
Sold or booked
48%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Salasar Mahavir Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MAHAVIR RESIDENCY0%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • MAHAVIR RESIDENCY: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Salasar Mahavir Residency every 1–2 months.

Salasar Mahavir Residency: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Salasar Mahavir Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Salasar Mahavir Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Salasar Mahavir Residency

What is the possession date of Salasar Mahavir Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Salasar Mahavir Residency in Adarsh Park, Thane is 4 October 2026 — 54 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

The date has already moved 54 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Salasar Mahavir Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Salasar Mahavir Residency's builder has filed on MahaRERA, the official one, is 4 October 2026, already 54 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Salasar Mahavir Residency extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Salasar Mahavir Residency's builder applied to MahaRERA to extend the completion date 5 times: to 29 December 2022, giving the reason "Project delayed due to covid situation."; to 29 December 2023, giving the reason "1. Project delayed due to covid situation"; to 31 December 2024, giving the reason "The building has completed in respect to all the construction activity and finishing work. Since the project has got the CRZ NOC in 2013, but due to change in alignment of CRZ line - 2019 changed as per the CRZ notification dated 25/08/2023, the clearance is yet to receive from the MCZMA Department, due to which our Occupation Certificate process is not able to proceed further."; to 31 December 2025, giving the reason "The building has completed in respect to all the construction activity and finishing work. We have already submitted Architect Certificate for 100% completion of project. The reason behind delay of Occupancy Certificate is that the project has got the CRZ NOC in 2013, but due to change in alignment of CRZ line - 2019 changed as per the CRZ notification dated 25/08/2023, the clearance is yet to receive from the MCZMA Department, due to which our Occupancy Certificate process is not able to proceed further. Bhiwandi Nizampur City Municipal Corporation also wrote a letter to MCZMA that in resp…"; to 4 June 2026, giving the reason "We, Shree Salasar Realty, the promoter of project “Mahavir Residency” having MahaRERA Registration No. P51700012556, hereby declare and confirm that there is no correction or change required in any of the project details submitted and available on the MahaRERA portal in respect of this project. We further request the Hon'ble Authority to kindly grant an extension of the MahaRERA Project Registration up to 4th June 2026, being the date of issuance of the Occupancy Certificate (OC) for the said project. Thanking You". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Salasar Mahavir Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Salasar Mahavir Residency in Adarsh Park, Thane is P51700012556.

Is Salasar Mahavir Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Salasar Mahavir Residency is registered as P51700012556 and its status is "Lapsed (registration period ended)".

What is the current construction status of Salasar Mahavir Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Salasar Mahavir Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MAHAVIR RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Salasar Mahavir Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Salasar Mahavir Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Salasar Mahavir Residency is registered on MahaRERA as P51700012556, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Salasar Mahavir Residency?

Salasar Mahavir Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Salasar Mahavir Residency?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Salasar Mahavir Residency: gharkundli.com/tools/property-cost-calculator

Has Salasar Mahavir Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Salasar Mahavir Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 4 October 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Salasar Mahavir Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Salasar Mahavir Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (4 October 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Salasar Mahavir Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Salasar Mahavir Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Salasar Mahavir Residency's possession date changes?

The latest dates are on Salasar Mahavir Residency's MahaRERA page (P51700012556). GharKundli's Kundli Watch sends a free WhatsApp update on Salasar Mahavir Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Salasar Mahavir Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Salasar Mahavir Residency has one building filed: MAHAVIR RESIDENCY with 13 floors and 44 units.

How much parking does Salasar Mahavir Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 10 covered car parking spaces for Salasar Mahavir Residency.

How big is the land of Salasar Mahavir Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Salasar Mahavir Residency stands on 1,649 sq m of land (about 0.4 acres), with 2,814 sq m of sanctioned built-up area and 239 sq m of recreational open space.

What are the reviews of Salasar Mahavir Residency?

Google Maps has reviews of Salasar Mahavir Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Salasar Mahavir Residency?

Salasar Mahavir Residency by SHREE SALASAR REALTY is in Adarsh Park, Thane, pincode 421302 (near Bhiwandi, Dandekarwadi), Maharashtra, and is registered on MahaRERA as P51700012556, per GharKundli's check of MahaRERA records. Its land is filed as 3538/1. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).

How many flats are in Salasar Mahavir Residency, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Salasar Mahavir Residency has 44 homes in 1 tower registered on MahaRERA, and 48% of them are sold or booked.

When was Salasar Mahavir Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Salasar Mahavir Residency was registered on MahaRERA on 4 September 2017. GharKundli did not find a title report on the land on file there.

Does Salasar Mahavir Residency have any legal issues or court cases?

No court cases are listed for Salasar Mahavir Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Salasar Mahavir Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SHREE SALASAR REALTY.

All projects with possession due in 2026 in Thane →

Other projects in Bhiwandi

All 382 projects in Bhiwandi (421302) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.