Pavanputra Apartments
by PAVANPUTRA APARTMENTS · Kalher, Thane 421302Also near Dandekarwadi
What’s in the report? →Possession date of Pavanputra Apartments (MahaRERA P51700020529): 30 July 2026, moved from 30 March 2022 (48 months later), and it has already passed. It has 120 homes, 57% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700020529. Status: Lapsed (registration period ended). Its completion date has moved from March 2022 to July 2026: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700020529, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (July 2026) has passed.
What do you want to know about Pavanputra Apartments?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Pavanputra Apartments has moved
30 March 2022
Completion date given when the project was registered
30 March 2023
Extended at the builder's request (MahaRERA application EXT51700011650)
Reason the builder gave MahaRERA: “The reason for the change is because previously the approval was for 9 floors and now we have been given approval for 11 floors.”
30 March 2024
Extended at the builder's request (MahaRERA application EXT51700015395)
Reason the builder gave MahaRERA:
“With respect to seeking extension under section 7(3) by 1 year, we wish to inform you that we have received additional 2 floor from existing proposed development of residential building from Competent authority (herein referred as "MMRDA").…” Read the full reason
“With respect to seeking extension under section 7(3) by 1 year, we wish to inform you that we have received additional 2 floor from existing proposed development of residential building from Competent authority (herein referred as "MMRDA"). Furthermore, we have modified total estimation of project cost in our form 3 according to new amendment of Proposed development. Henceforth, we are request you to grant additional extension by 1 year to complete remaining part of project. We obtained requisite assent from our customers who have booking and investing in our Project.”30 March 2026
Extended at the builder's request (MahaRERA application EXT51700025086)
Reason the builder gave MahaRERA:
“Respected Sir/Ma’am, I am writing to inform you that the Pavanputra Apartments have not yet received the Occupancy Certificate (OC) from the concerned authorities. As you are aware, the OC is a crucial document required for the formal posse…” Read the full reason
“Respected Sir/Ma’am, I am writing to inform you that the Pavanputra Apartments have not yet received the Occupancy Certificate (OC) from the concerned authorities. As you are aware, the OC is a crucial document required for the formal possession of the property and completion of the project under the Maharashtra Real Estate Regulatory Authority (MAHARA) guidelines. Due to the delay in obtaining the Occupancy Certificate, we are unable to meet the prescribed timelines for the completion of the project. We had applied for the OC on [date], which was well before the extended timeline for compl…”30 July 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Pavanputra Apartments’s extension records on MahaRERA (P51700020529), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Pavanputra Apartments
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700020529
- Status
- Lapsed (registration period ended)
- Builder
- PAVANPUTRA APARTMENTS
- Location
- Kalher, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 18 Apr 2019
- Completion date at registration
- March 2022
- Latest completion date
- July 2026
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 120
- Sold or booked
- 57%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Pavanputra Apartments, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PAVANPUTRA APARTMENTS | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- PAVANPUTRA APARTMENTS: covers STILT
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pavanputra Apartments every 1–2 months.
Pavanputra Apartments: buildings, flats and land, as filed on MahaRERA
- Buildings: PAVANPUTRA APARTMENTS (13 floors, 120 units)
- Land: 4,309 sq m (about 1.1 acres) · sanctioned built-up 4,177 sq m · recreational space 4,177 sq m
- Land, as filed: SURVEY 101, 102, 103
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Pavanputra Apartments →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Pavanputra Apartments: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Pavanputra Apartments
What is the possession date of Pavanputra Apartments?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Pavanputra Apartments in Kalher, Thane is 30 July 2026 — 48 months later than 30 March 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.
The date has already moved 48 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Pavanputra Apartments?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Pavanputra Apartments's builder has filed on MahaRERA, the official one, is 30 July 2026, already 48 months later than the 30 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Pavanputra Apartments extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Pavanputra Apartments's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2023, giving the reason "The reason for the change is because previously the approval was for 9 floors and now we have been given approval for 11 floors."; to 30 March 2024, giving the reason "With respect to seeking extension under section 7(3) by 1 year, we wish to inform you that we have received additional 2 floor from existing proposed development of residential building from Competent authority (herein referred as "MMRDA"). Furthermore, we have modified total estimation of project cost in our form 3 according to new amendment of Proposed development. Henceforth, we are request you to grant additional extension by 1 year to complete remaining part of project. We obtained requisite assent from our customers who have booking and investing in our Project."; to 30 March 2026, giving the reason "Respected Sir/Ma’am, I am writing to inform you that the Pavanputra Apartments have not yet received the Occupancy Certificate (OC) from the concerned authorities. As you are aware, the OC is a crucial document required for the formal possession of the property and completion of the project under the Maharashtra Real Estate Regulatory Authority (MAHARA) guidelines. Due to the delay in obtaining the Occupancy Certificate, we are unable to meet the prescribed timelines for the completion of the project. We had applied for the OC on [date], which was well before the extended timeline for compl…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Pavanputra Apartments?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Pavanputra Apartments in Kalher, Thane is P51700020529.
Is Pavanputra Apartments registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pavanputra Apartments is registered as P51700020529 and its status is "Lapsed (registration period ended)".
What is the current construction status of Pavanputra Apartments? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Pavanputra Apartments's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on PAVANPUTRA APARTMENTS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Pavanputra Apartments have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Pavanputra Apartments safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Pavanputra Apartments is registered on MahaRERA as P51700020529, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 48 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Pavanputra Apartments?
Pavanputra Apartments isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Pavanputra Apartments?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Pavanputra Apartments: gharkundli.com/tools/property-cost-calculator
Has Pavanputra Apartments received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Pavanputra Apartments isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Pavanputra Apartments?
According to GharKundli's check of MahaRERA records (updated October 2026), Pavanputra Apartments's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Pavanputra Apartments uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Pavanputra Apartments was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Pavanputra Apartments's possession date changes?
The latest dates are on Pavanputra Apartments's MahaRERA page (P51700020529). GharKundli's Kundli Watch sends a free WhatsApp update on Pavanputra Apartments every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Pavanputra Apartments have?
According to GharKundli's check of MahaRERA records (updated October 2026), Pavanputra Apartments has one building filed: PAVANPUTRA APARTMENTS with 13 floors and 120 units.
How big is the land of Pavanputra Apartments?
According to GharKundli's check of MahaRERA records (updated October 2026), Pavanputra Apartments stands on 4,309 sq m of land (about 1.1 acres), with 4,177 sq m of sanctioned built-up area and 4,177 sq m of recreational open space.
What are the reviews of Pavanputra Apartments?
Google Maps has reviews of Pavanputra Apartments written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Pavanputra Apartments?
Pavanputra Apartments by PAVANPUTRA APARTMENTS is in Kalher, Thane, pincode 421302 (near Dandekarwadi), Maharashtra, and is registered on MahaRERA as P51700020529, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY 101, 102, 103. GharKundli lists all 382 MahaRERA projects in Bhiwandi (421302).
How many flats are in Pavanputra Apartments, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Pavanputra Apartments has 120 homes in 1 tower registered on MahaRERA, and 57% of them are sold or booked.
When was Pavanputra Apartments registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Pavanputra Apartments was registered on MahaRERA on 18 April 2019. GharKundli did not find a title report on the land on file there.
Does Pavanputra Apartments have any legal issues or court cases?
No court cases are listed for Pavanputra Apartments on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Pavanputra Apartments?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PAVANPUTRA APARTMENTS.
Check it yourself on MahaRERA
- How to check the possession date of Pavanputra Apartments
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Thane →
Other projects in Bhiwandi (421302)
- Ashoka Complex
- Kohinoor Uptown T1 & T6
- Arihant City Phase-ii - K Building
- Regal Square PH 4 Tower 6 and 8
- Royal Park
- Sai Deep Residency
- Raghunath Heights
- Neelkanth Sadan
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.