Akshar Atmiya Residency
by AKSHAR INFRA · Ambernath, Thane 421503Registered on MahaRERA as “ATMIYA RESIDENCY”
What’s in the report? →Possession date of Akshar Atmiya Residency (MahaRERA P51700024195): 30 April 2028, moved from 30 December 2025 (24 months later). It has 241 homes, 74% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700024195, and currently active. Its completion date has moved from December 2025 to April 2028: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700024195, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Akshar Atmiya Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Akshar Atmiya Residency has moved
30 December 2025
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA28012619597)
Reason the builder gave MahaRERA:
“We,partners of Akshar Infra want to inform you that the progress of construction for the above mentioned project has been slower than originally scheduled due to slower than anticipated booking and sale of flats.The pace of bookings directl…” Read the full reason
“We,partners of Akshar Infra want to inform you that the progress of construction for the above mentioned project has been slower than originally scheduled due to slower than anticipated booking and sale of flats.The pace of bookings directly impacts the project's cash flow,which in turn affects the timely mobilization of resources,procurement of materials,and engagement of contractors.Despite our contionus marketing efforts & strategic initiaves to improve sales,market conditiones have remained challenging, reulting in reduced inflows during the relevant period.Due to reduced inflows,we are…”30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Akshar Atmiya Residency’s extension records on MahaRERA (P51700024195), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Akshar Atmiya Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700024195
- Status
- Registered and active
- Builder
- AKSHAR INFRA
- Location
- Ambernath, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 24 Jan 2020
- Completion date at registration
- December 2025
- Latest completion date
- April 2028
- Delay so far
- 24 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 241
- Sold or booked
- 74%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Akshar Atmiya Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A Wing | 100% | 100% | 100% | 100% |
| B-WING | 100% | 100% | 100% | 100% |
| C-WING | 100% | 25% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- A Wing: covers 7 floors
- B-WING: covers 7 floors
- C-WING: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Akshar Atmiya Residency every 1–2 months.
Akshar Atmiya Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: A Wing (9 floors, 84 units) · B-WING (9 floors, 85 units) · C-WING (9 floors, 72 units)
- Land: 6,750 sq m (about 1.7 acres) · sanctioned built-up 7,897 sq m
- Land, as filed: PLOT 75/2 and 77 and 74 and 75/1
- Map: Get directions
The builder’s record and reviews
Akshar Group (a group of 7 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 12 months); 4 still being built, 2 past the promised date (typically 5 months late); 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Akshar Atmiya Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Akshar Atmiya Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Akshar Atmiya Residency
What is the possession date of Akshar Atmiya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Akshar Atmiya Residency in Ambernath, Thane is 30 April 2028 — 24 months later than 30 December 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Akshar Atmiya Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Akshar Atmiya Residency's builder has filed on MahaRERA, the official one, is 30 April 2028, already 24 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Akshar Atmiya Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Atmiya Residency's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "We,partners of Akshar Infra want to inform you that the progress of construction for the above mentioned project has been slower than originally scheduled due to slower than anticipated booking and sale of flats.The pace of bookings directly impacts the project's cash flow,which in turn affects the timely mobilization of resources,procurement of materials,and engagement of contractors.Despite our contionus marketing efforts & strategic initiaves to improve sales,market conditiones have remained challenging, reulting in reduced inflows during the relevant period.Due to reduced inflows,we are…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Akshar Atmiya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Akshar Atmiya Residency in Ambernath, Thane is P51700024195.
Is Akshar Atmiya Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Atmiya Residency is registered as P51700024195 and its status is "Registered and active".
What is the current construction status of Akshar Atmiya Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Atmiya Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 25% to 100% across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Akshar Atmiya Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Akshar Atmiya Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Atmiya Residency is registered on MahaRERA as P51700024195, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Akshar Atmiya Residency?
Akshar Atmiya Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Akshar Atmiya Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Akshar Atmiya Residency: gharkundli.com/tools/property-cost-calculator
Has Akshar Atmiya Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Atmiya Residency is still under construction, with 30 April 2028 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Akshar Atmiya Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Akshar Atmiya Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Akshar Atmiya Residency's possession date changes?
The latest dates are on Akshar Atmiya Residency's MahaRERA page (P51700024195). GharKundli's Kundli Watch sends a free WhatsApp update on Akshar Atmiya Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Akshar Atmiya Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Atmiya Residency has 3 buildings filed: A Wing with 9 floors and 84 units; B-WING with 9 floors and 85 units; C-WING with 9 floors and 72 units.
How big is the land of Akshar Atmiya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Atmiya Residency stands on 6,750 sq m of land (about 1.7 acres), with 7,897 sq m of sanctioned built-up area.
What is the track record of Akshar Atmiya Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Group (a group of 7 linked companies) has 8 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 12 months); 4 still being built, 2 past the promised date (typically 5 months late); 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Akshar Atmiya Residency?
Google Maps has reviews of Akshar Atmiya Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Akshar Atmiya Residency?
Akshar Atmiya Residency by AKSHAR INFRA is in Ambernath, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700024195, per GharKundli's check of MahaRERA records. Its land is filed as PLOT 75/2 and 77 and 74 and 75/1. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Akshar Atmiya Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Atmiya Residency has 241 homes in 3 towers registered on MahaRERA, and 74% of them are sold or booked.
When was Akshar Atmiya Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Akshar Atmiya Residency was registered on MahaRERA on 24 January 2020. GharKundli did not find a title report on the land on file there.
Does Akshar Atmiya Residency have any legal issues or court cases?
No court cases are listed for Akshar Atmiya Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Akshar Atmiya Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AKSHAR INFRA.
Check it yourself on MahaRERA
- How to check the possession date of Akshar Atmiya Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Thane →
Other projects in Kulgaon (421503)
- New Neelgagan CHS
- Redevlopment of Panvelkar Empire Wing A Wing A-1 Wing B
- Aditya Matruchaya
- Shree Hill Residency
- Shree Samarth Krupa Prasad Co Operative Housing Society Limited
- V A Business Centre
- Sai Darshan
- Skyrise Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.