Shree Samarth Krupa Prasad Co Operative Housing Society Limited
by RAJLAXMI SAMARTH DEVELOPERS · Ambernath, Thane 421503
What’s in the report? →Possession: Shree Samarth Krupa Prasad Co Operative Housing Society Limited (MahaRERA P51700032714) is marked completed on MahaRERA. It has 56 homes, 66% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700032714. Status: Completed.
Source: MahaRERA website — records for P51700032714, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Shree Samarth Krupa Prasad Co Operative Housing Society Limited?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Shree Samarth Krupa Prasad Co Operative Housing Society Limited has moved
31 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA24032620348)
Reason the builder gave MahaRERA: “Dear Team, our project is completed and oc also received we would like to update our pending details in project tab, so we request you to please extend our project date.”
Source: Shree Samarth Krupa Prasad Co Operative Housing Society Limited’s extension records on MahaRERA (P51700032714), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shree Samarth Krupa Prasad Co Operative Housing Society Limited
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700032714
- Status
- Completed
- Builder
- RAJLAXMI SAMARTH DEVELOPERS
- Location
- Ambernath, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 24 Jan 2022
- Completion date at registration
- December 2025
- Latest completion date
- June 2026
- Delay so far
- 6 months
- Homes
- 56
- Sold or booked
- 66%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Shree Samarth Krupa Prasad Co Operative Housing Society Limited, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE SAMARTH KRUPA PRASAD A WING | 100% | 100% | 100% | 100% |
| SHREE SAMARTH KRUPA PRASAD B WING | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- SHREE SAMARTH KRUPA PRASAD A WING: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shree Samarth Krupa Prasad Co Operative Housing Society Limited every 1–2 months.
Shree Samarth Krupa Prasad Co Operative Housing Society Limited: buildings, flats and land, as filed on MahaRERA
- Buildings: SHREE SAMARTH KRUPA PRASAD A WING (7 floors, 39 units) · SHREE SAMARTH KRUPA PRASAD B WING (6 floors, 20 units)
- Car parking: 8 covered
- Land: 910 sq m (about 0.2 acres) · sanctioned built-up 2,466 sq m
- Land, as filed: S NO 5, H NO 2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shree Samarth Krupa Prasad Co Operative Housing Society Limited →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shree Samarth Krupa Prasad Co Operative Housing Society Limited: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Shree Samarth Krupa Prasad Co Operative Housing Society Limited
What is the possession date of Shree Samarth Krupa Prasad Co Operative Housing Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shree Samarth Krupa Prasad Co Operative Housing Society Limited in Ambernath, Thane is 30 June 2026 — 6 months later than 31 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Shree Samarth Krupa Prasad Co Operative Housing Society Limited?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shree Samarth Krupa Prasad Co Operative Housing Society Limited's builder has filed on MahaRERA, the official one, is 30 June 2026, already 6 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Shree Samarth Krupa Prasad Co Operative Housing Society Limited extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "Dear Team, our project is completed and oc also received we would like to update our pending details in project tab, so we request you to please extend our project date.".
What is the RERA number of Shree Samarth Krupa Prasad Co Operative Housing Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shree Samarth Krupa Prasad Co Operative Housing Society Limited in Ambernath, Thane is P51700032714.
Is Shree Samarth Krupa Prasad Co Operative Housing Society Limited registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited is registered as P51700032714 and its status is "Completed".
What is the current construction status of Shree Samarth Krupa Prasad Co Operative Housing Society Limited? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Shree Samarth Krupa Prasad Co Operative Housing Society Limited have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shree Samarth Krupa Prasad Co Operative Housing Society Limited safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited is registered on MahaRERA as P51700032714, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Shree Samarth Krupa Prasad Co Operative Housing Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.
What is the stamp duty and registration cost for a flat in Shree Samarth Krupa Prasad Co Operative Housing Society Limited?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Shree Samarth Krupa Prasad Co Operative Housing Society Limited: gharkundli.com/tools/property-cost-calculator
Has Shree Samarth Krupa Prasad Co Operative Housing Society Limited received its OC? Is it ready to move in?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra
When was Shree Samarth Krupa Prasad Co Operative Housing Society Limited completed?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited is marked completed on MahaRERA, and the completion date filed there is 30 June 2026. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.
Is Shree Samarth Krupa Prasad Co Operative Housing Society Limited a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited is a redevelopment: 27 of its flats are set aside for existing occupants (rehab), and the rest are for sale. Its planning authority is KULGAON BADLAPUR NAGARPARISHAD, not the Slum Rehabilitation Authority, so it isn't an SRA scheme.
Has Shree Samarth Krupa Prasad Co Operative Housing Society Limited uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Shree Samarth Krupa Prasad Co Operative Housing Society Limited was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Shree Samarth Krupa Prasad Co Operative Housing Society Limited's possession date changes?
The latest dates are on Shree Samarth Krupa Prasad Co Operative Housing Society Limited's MahaRERA page (P51700032714). GharKundli's Kundli Watch sends a free WhatsApp update on Shree Samarth Krupa Prasad Co Operative Housing Society Limited every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shree Samarth Krupa Prasad Co Operative Housing Society Limited have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited has 2 buildings filed: SHREE SAMARTH KRUPA PRASAD A WING with 7 floors and 39 units; SHREE SAMARTH KRUPA PRASAD B WING with 6 floors and 20 units.
How much parking does Shree Samarth Krupa Prasad Co Operative Housing Society Limited have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 8 covered car parking spaces for Shree Samarth Krupa Prasad Co Operative Housing Society Limited.
How big is the land of Shree Samarth Krupa Prasad Co Operative Housing Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited stands on 910 sq m of land (about 0.2 acres), with 2,466 sq m of sanctioned built-up area.
What are the reviews of Shree Samarth Krupa Prasad Co Operative Housing Society Limited?
Google Maps has reviews of Shree Samarth Krupa Prasad Co Operative Housing Society Limited written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Shree Samarth Krupa Prasad Co Operative Housing Society Limited?
Shree Samarth Krupa Prasad Co Operative Housing Society Limited by RAJLAXMI SAMARTH DEVELOPERS is in Ambernath, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700032714, per GharKundli's check of MahaRERA records. Its land is filed as S NO 5, H NO 2. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Shree Samarth Krupa Prasad Co Operative Housing Society Limited, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited has 56 homes in 2 towers registered on MahaRERA, and 66% of them are sold or booked.
When was Shree Samarth Krupa Prasad Co Operative Housing Society Limited registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shree Samarth Krupa Prasad Co Operative Housing Society Limited was registered on MahaRERA on 24 January 2022. GharKundli did not find a title report on the land on file there.
Does Shree Samarth Krupa Prasad Co Operative Housing Society Limited have any legal issues or court cases?
No court cases are listed for Shree Samarth Krupa Prasad Co Operative Housing Society Limited on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Shree Samarth Krupa Prasad Co Operative Housing Society Limited?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAJLAXMI SAMARTH DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Shree Samarth Krupa Prasad Co Operative Housing Society Limited
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kulgaon (421503)
- New Neelgagan CHS
- Aditya Matruchaya
- Redevlopment of Panvelkar Empire Wing A Wing A-1 Wing B
- Shree Hill Residency
- Atmiya Residency
- V A Business Centre
- Sai Darshan
- Skyrise Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.