Possession date of Krupa Sai Darshan (MahaRERA P51700049948): 30 November 2026, moved from 31 December 2025 (11 months later). It has 77 homes, 51% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51700049948, and currently active.

Source: MahaRERA website — records for P51700049948, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Krupa Sai Darshan?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Krupa Sai Darshan has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 November 2026

    Extended at the builder's request (MahaRERA application EA24012619572)

    Reason the builder gave MahaRERA: “DUE TO NOT ABLE TO COMPLETE CONSTRUCTION AND REQUESTED TO EXTEND FOR MORE 11 MONTHS ONLY”

Source: Krupa Sai Darshan’s extension records on MahaRERA (P51700049948), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Krupa Sai Darshan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the November 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51700049948
Status
Registered and active
Builder
SAI KRUPA BUILDERS
Location
Ambernath, Thane · 421503
Project type
Others
Registered on
6 Mar 2023
Completion date at registration
December 2025
Latest completion date
November 2026
Delay so far
11 months
Homes
77
Sold or booked
51%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of Krupa Sai Darshan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI DARSHAN100%100%95%25%

Commencement certificate (CC), as filed on MahaRERA

  • SAI DARSHAN: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Krupa Sai Darshan every 1–2 months.

Krupa Sai Darshan: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI DARSHAN (31 floors, 85 units)
  • Car parking: 30 covered
  • Land: 1,740 sq m (about 0.4 acres) · sanctioned built-up 4,864 sq m
  • Land, as filed: SURVEY NO 18 HISSA NO 1
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Krupa Sai Darshan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Krupa Sai Darshan: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Krupa Sai Darshan

What is the possession date of Krupa Sai Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Krupa Sai Darshan in Ambernath, Thane is 30 November 2026 — 11 months later than 31 December 2025, the date given at registration.

The date has already moved 11 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Krupa Sai Darshan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Krupa Sai Darshan's builder has filed on MahaRERA, the official one, is 30 November 2026, already 11 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Krupa Sai Darshan extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Krupa Sai Darshan's builder applied to MahaRERA to extend the completion date once: to 30 November 2026, giving the reason "DUE TO NOT ABLE TO COMPLETE CONSTRUCTION AND REQUESTED TO EXTEND FOR MORE 11 MONTHS ONLY".

What is the RERA number of Krupa Sai Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Krupa Sai Darshan in Ambernath, Thane is P51700049948.

Is Krupa Sai Darshan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Krupa Sai Darshan is registered as P51700049948 and its status is "Registered and active".

What is the current construction status of Krupa Sai Darshan? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Krupa Sai Darshan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI DARSHAN is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does Krupa Sai Darshan have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Krupa Sai Darshan safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Krupa Sai Darshan is registered on MahaRERA as P51700049948, its completion date has moved 11 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Krupa Sai Darshan?

Krupa Sai Darshan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Krupa Sai Darshan?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Krupa Sai Darshan: gharkundli.com/tools/property-cost-calculator

Has Krupa Sai Darshan received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Krupa Sai Darshan is still under construction, with 30 November 2026 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

Has Krupa Sai Darshan uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Krupa Sai Darshan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Krupa Sai Darshan's possession date changes?

The latest dates are on Krupa Sai Darshan's MahaRERA page (P51700049948). GharKundli's Kundli Watch sends a free WhatsApp update on Krupa Sai Darshan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Krupa Sai Darshan have?

According to GharKundli's check of MahaRERA records (updated October 2026), Krupa Sai Darshan has one building filed: SAI DARSHAN with 31 floors and 85 units.

How much parking does Krupa Sai Darshan have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 30 covered car parking spaces for Krupa Sai Darshan.

How big is the land of Krupa Sai Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), Krupa Sai Darshan stands on 1,740 sq m of land (about 0.4 acres), with 4,864 sq m of sanctioned built-up area.

What are the reviews of Krupa Sai Darshan?

Google Maps has reviews of Krupa Sai Darshan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Krupa Sai Darshan?

Krupa Sai Darshan by SAI KRUPA BUILDERS is in Ambernath, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700049948, per GharKundli's check of MahaRERA records. Its land is filed as SURVEY NO 18 HISSA NO 1. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).

How many flats are in Krupa Sai Darshan, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Krupa Sai Darshan has 77 homes in 1 tower registered on MahaRERA, and 51% of them are sold or booked.

When was Krupa Sai Darshan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Krupa Sai Darshan was registered on MahaRERA on 6 March 2023. GharKundli did not find a title report on the land on file there.

Does Krupa Sai Darshan have any legal issues or court cases?

No court cases are listed for Krupa Sai Darshan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Krupa Sai Darshan?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SAI KRUPA BUILDERS, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2026 in Thane →

Other projects in Kulgaon (421503)

All 938 projects in Kulgaon (421503) →

Other projects by SAI KRUPA BUILDERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.