Sadguru Shree Hill Residency
by SADGURU CORPORATION · Ambernath, Thane 421503Registered on MahaRERA as “SHREE HILL RESIDENCY”
What’s in the report? →Possession date of Sadguru Shree Hill Residency (MahaRERA P51700055920): 31 July 2027, moved from 31 March 2026 (12 months later). It has 30 homes, 20% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700055920, and currently active. Its completion date has moved from March 2026 to July 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51700055920, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Sadguru Shree Hill Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Sadguru Shree Hill Residency has moved
31 March 2026
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA06032620117)
Reason the builder gave MahaRERA: “We had expected a sale around 60 % of our inventory, but due to slow down in market we are to sell only one flat in full project and we have completed 80 % of work.”
31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Sadguru Shree Hill Residency’s extension records on MahaRERA (P51700055920), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Sadguru Shree Hill Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700055920
- Status
- Registered and active
- Builder
- SADGURU CORPORATION
- Location
- Ambernath, Thane · 421503
- Project type
- Residential / Group Housing
- Registered on
- 29 Apr 2024
- Completion date at registration
- March 2026
- Latest completion date
- July 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 30
- Sold or booked
- 20%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Sadguru Shree Hill Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING B | 100% | 100% | 50% | 10% |
Commencement certificate (CC), as filed on MahaRERA
- WING B: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sadguru Shree Hill Residency every 1–2 months.
Sadguru Shree Hill Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: WING B (8 floors, 30 units)
- Land: 959 sq m (about 0.2 acres) · sanctioned built-up 1,373 sq m
- Land, as filed: S. NO. 76, HISSA NO. 11,12(PT),13,18 & 19 PLOT NO. A
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Sadguru Shree Hill Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Sadguru Shree Hill Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Sadguru Shree Hill Residency
What is the possession date of Sadguru Shree Hill Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Sadguru Shree Hill Residency in Ambernath, Thane is 31 July 2027 — 12 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Sadguru Shree Hill Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Sadguru Shree Hill Residency's builder has filed on MahaRERA, the official one, is 31 July 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Sadguru Shree Hill Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Shree Hill Residency's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "We had expected a sale around 60 % of our inventory, but due to slow down in market we are to sell only one flat in full project and we have completed 80 % of work.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Sadguru Shree Hill Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Sadguru Shree Hill Residency in Ambernath, Thane is P51700055920.
Is Sadguru Shree Hill Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Shree Hill Residency is registered as P51700055920 and its status is "Registered and active".
What is the current construction status of Sadguru Shree Hill Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Shree Hill Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on WING B is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.
Does Sadguru Shree Hill Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Sadguru Shree Hill Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Shree Hill Residency is registered on MahaRERA as P51700055920, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Sadguru Shree Hill Residency?
Sadguru Shree Hill Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) inside the Mumbai Metropolitan Region, or 90 sq m elsewhere, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Sadguru Shree Hill Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Sadguru Shree Hill Residency: gharkundli.com/tools/property-cost-calculator
Has Sadguru Shree Hill Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Shree Hill Residency is still under construction, with 31 July 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Sadguru Shree Hill Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Sadguru Shree Hill Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Sadguru Shree Hill Residency's possession date changes?
The latest dates are on Sadguru Shree Hill Residency's MahaRERA page (P51700055920). GharKundli's Kundli Watch sends a free WhatsApp update on Sadguru Shree Hill Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Sadguru Shree Hill Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Shree Hill Residency has one building filed: WING B with 8 floors and 30 units.
How big is the land of Sadguru Shree Hill Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Shree Hill Residency stands on 959 sq m of land (about 0.2 acres), with 1,373 sq m of sanctioned built-up area.
What are the reviews of Sadguru Shree Hill Residency?
Google Maps has reviews of Sadguru Shree Hill Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Sadguru Shree Hill Residency?
Sadguru Shree Hill Residency by SADGURU CORPORATION is in Ambernath, Thane, pincode 421503, Maharashtra, and is registered on MahaRERA as P51700055920, per GharKundli's check of MahaRERA records. Its land is filed as S. NO. 76, HISSA NO. 11,12(PT),13,18 & 19 PLOT NO. A. GharKundli lists all 938 MahaRERA projects in Kulgaon (421503).
How many flats are in Sadguru Shree Hill Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Shree Hill Residency has 30 homes in 1 tower registered on MahaRERA, and 20% of them are sold or booked.
When was Sadguru Shree Hill Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Sadguru Shree Hill Residency was registered on MahaRERA on 29 April 2024. GharKundli did not find a title report on the land on file there.
Does Sadguru Shree Hill Residency have any legal issues or court cases?
No court cases are listed for Sadguru Shree Hill Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Sadguru Shree Hill Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SADGURU CORPORATION.
Check it yourself on MahaRERA
- How to check the possession date of Sadguru Shree Hill Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Thane →
Other projects in Kulgaon (421503)
- New Neelgagan CHS
- Aditya Matruchaya
- Redevlopment of Panvelkar Empire Wing A Wing A-1 Wing B
- Shree Samarth Krupa Prasad Co Operative Housing Society Limited
- Atmiya Residency
- V A Business Centre
- Sai Darshan
- Skyrise Residency
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.