by AL AMEEN BUILDERS AND DEVELOPERS · Ratnagiri

Possession date of HERITAGE RATNA: 30 April 2027, moved from 20 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52800033644, and currently active. Its completion date has moved from December 2024 to April 2027: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about HERITAGE RATNA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HERITAGE RATNA has moved

  1. 20 December 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT52800027536)

    Reason the builder gave MahaRERA:
    “1. After the Commencement of Project, an objection was raised by the old Tenants of the plot in the District Court, due to which the Court ordered stay on the Construction work for approximately 10 months. The stay order was cancelled when…” Read the full reason“1. After the Commencement of Project, an objection was raised by the old Tenants of the plot in the District Court, due to which the Court ordered stay on the Construction work for approximately 10 months. The stay order was cancelled when the dispute was settled with the Tenants after which we were able to commence the Project. 2. Work was also delayed due to holidays and absenties by labours and contractors, due to Local Festivals. Therefore we will need an Extension till 31/12/2026”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: HERITAGE RATNA’s extension records on MahaRERA (P52800033644), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HERITAGE RATNA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52800033644
Status
Registered and active
Builder
AL AMEEN BUILDERS AND DEVELOPERS
Location
Ratnagiri · 415612
Project type
Others
Registered on
2 Mar 2022
Completion date at registration
December 2024
Latest completion date
April 2027
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
66
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of HERITAGE RATNA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
HERITAGE RATNA0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HERITAGE RATNA every month.

HERITAGE RATNA: buildings, flats and land, as filed on MahaRERA

  • Buildings: HERITAGE RATNA (9 floors)
  • Land: 1,088 sq m (about 0.3 acres) · sanctioned built-up 3,863 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of HERITAGE RATNA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HERITAGE RATNA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HERITAGE RATNA

What is the possession date of HERITAGE RATNA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for HERITAGE RATNA in Ratnagiri is 30 April 2027 — 24 months later than 20 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for HERITAGE RATNA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HERITAGE RATNA's builder has filed on MahaRERA, the official one, is 30 April 2027, already 24 months later than the 20 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of HERITAGE RATNA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), HERITAGE RATNA's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "1. After the Commencement of Project, an objection was raised by the old Tenants of the plot in the District Court, due to which the Court ordered stay on the Construction work for approximately 10 months. The stay order was cancelled when the dispute was settled with the Tenants after which we were able to commence the Project. 2. Work was also delayed due to holidays and absenties by labours and contractors, due to Local Festivals. Therefore we will need an Extension till 31/12/2026". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of HERITAGE RATNA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of HERITAGE RATNA in Ratnagiri is P52800033644.

Is HERITAGE RATNA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HERITAGE RATNA is registered as P52800033644 and its status is "Registered and active".

What is the construction status of HERITAGE RATNA?

According to GharKundli's check of MahaRERA records (updated October 2026), HERITAGE RATNA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on HERITAGE RATNA is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does HERITAGE RATNA have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is HERITAGE RATNA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), HERITAGE RATNA is registered on MahaRERA as P52800033644, its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HERITAGE RATNA's possession date changes?

The latest dates are on HERITAGE RATNA's MahaRERA page (P52800033644). GharKundli's Kundli Watch sends a free WhatsApp update on HERITAGE RATNA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HERITAGE RATNA have?

According to GharKundli's check of MahaRERA records (updated October 2026), HERITAGE RATNA has one building filed: HERITAGE RATNA with 9 floors.

How big is the land of HERITAGE RATNA?

According to GharKundli's check of MahaRERA records (updated October 2026), HERITAGE RATNA stands on 1,088 sq m of land (about 0.3 acres), with 3,863 sq m of sanctioned built-up area.

Where can I read reviews of HERITAGE RATNA?

Google Maps has reviews of HERITAGE RATNA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HERITAGE RATNA?

HERITAGE RATNA by AL AMEEN BUILDERS AND DEVELOPERS is in Ratnagiri (pincode 415612), Maharashtra, and is registered on MahaRERA as P52800033644, per GharKundli's check of MahaRERA records.

How many homes are in HERITAGE RATNA?

According to GharKundli's check of MahaRERA records (updated October 2026), HERITAGE RATNA has 66 homes in 1 tower registered on MahaRERA.

When was HERITAGE RATNA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), HERITAGE RATNA was registered on MahaRERA on 2 March 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on HERITAGE RATNA?

No court cases are listed for HERITAGE RATNA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of HERITAGE RATNA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AL AMEEN BUILDERS AND DEVELOPERS, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Ratnagiri →

Other projects in pincode 415612

All 63 projects in Ratnagiri (415612) →

Other projects by AL AMEEN BUILDERS AND DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.