Balaji Uphomes
by Dhanveer Enterprises · Dombivli, Thane
Possession date of Balaji Uphomes: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700055656, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Balaji Uphomes?
How the possession date of Balaji Uphomes has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Balaji Uphomes’s extension records on MahaRERA (P51700055656), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Balaji Uphomes
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700055656
- Status
- Registered and active
- Builder
- Dhanveer Enterprises
- Location
- Dombivli, Thane · 421204
- Project type
- Residential / Group Housing
- Registered on
- 5 Apr 2024
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 673
- Sold or booked
- 25%
- Towers
- 3
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Balaji Uphomes, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 1 Wing A | 100% | 0% | 0% | 0% |
| Building No 1 Wing B | 100% | 0% | 0% | 0% |
| Building 2 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Building No 1 Wing A: covers 14 floors
- Building No 1 Wing B: covers 14 floors
- Building 2: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Balaji Uphomes every month.
Balaji Uphomes: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 1 Wing A (14 floors, 157 units) · Building No 1 Wing B (14 floors, 157 units) · Building 2 (8 floors, 359 units)
- Car parking: 55 covered, 92 open
- Land: 8,750 sq m (about 2.2 acres) · sanctioned built-up 14,901 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Balaji Uphomes →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Balaji Uphomes: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Balaji Uphomes
What is the possession date of Balaji Uphomes?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Balaji Uphomes in Dombivli, Thane is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Balaji Uphomes?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Balaji Uphomes's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Balaji Uphomes?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Balaji Uphomes in Dombivli, Thane is P51700055656.
Is Balaji Uphomes registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Uphomes is registered as P51700055656 and its status is "Registered and active".
What is the construction status of Balaji Uphomes?
According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Uphomes's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 0% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does Balaji Uphomes have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Balaji Uphomes safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Uphomes is registered on MahaRERA as P51700055656, its completion date has not been moved by the builder and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Balaji Uphomes's possession date changes?
The latest dates are on Balaji Uphomes's MahaRERA page (P51700055656). GharKundli's Kundli Watch sends a free WhatsApp update on Balaji Uphomes every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Balaji Uphomes have?
According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Uphomes has 3 buildings filed: Building No 1 Wing A with 14 floors and 157 units; Building No 1 Wing B with 14 floors and 157 units; Building 2 with 8 floors and 359 units.
How much parking does Balaji Uphomes have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 55 covered and 92 open car parking spaces for Balaji Uphomes.
How big is the land of Balaji Uphomes?
According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Uphomes stands on 8,750 sq m of land (about 2.2 acres), with 14,901 sq m of sanctioned built-up area.
Where can I read reviews of Balaji Uphomes?
Google Maps has reviews of Balaji Uphomes written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Balaji Uphomes?
Balaji Uphomes by Dhanveer Enterprises is in Dombivli, Thane (pincode 421204), Maharashtra, and is registered on MahaRERA as P51700055656, per GharKundli's check of MahaRERA records.
How many homes are in Balaji Uphomes?
According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Uphomes has 673 homes in 3 towers registered on MahaRERA, and 25% of them are sold or booked.
When was Balaji Uphomes registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Balaji Uphomes was registered on MahaRERA on 5 April 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Balaji Uphomes?
No court cases are listed for Balaji Uphomes on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Balaji Uphomes?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Dhanveer Enterprises.
Check it yourself on MahaRERA
- How to check the possession date of Balaji Uphomes
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in Dombivli
- Regency Luxuria Phase II
- SHIV PRARAMBH
- Mellennium Dreams
- Sarthi Serenity
- REGENCY ANANTAM NXT PHASE I
- Yashashree Arcade
- Runwal Gardens Phase 3 Bldg No 27-28
- Runwal Gardens Phase 4 Bldg No. 31-32
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.