NAAZ PLAZA
by PRESTIGE REALITY · At Mamdapur, Raigarh
Possession date of NAAZ PLAZA: 30 January 2027, moved from 30 June 2025 (15 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000046744, and currently active. Its completion date has moved from June 2025 to January 2027: 15 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about NAAZ PLAZA?
How the possession date of NAAZ PLAZA has moved
30 June 2025
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EA23072502135)
Reason the builder gave MahaRERA: “1) Poor booking response from customer. 2) Because of poor response our work was very slow. But now we have completed our 98 % Project”
30 September 2026
Extended at the builder's request (MahaRERA application EA05032620108)
Reason the builder gave MahaRERA: “1) Poor booking response from customer. 2) Because of poor response our work was very slow.”
30 January 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: NAAZ PLAZA’s extension records on MahaRERA (P52000046744), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on NAAZ PLAZA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the January 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000046744
- Status
- Registered and active
- Builder
- PRESTIGE REALITY
- Location
- At Mamdapur, Raigarh · 410101
- Project type
- Others
- Registered on
- 5 Sep 2022
- Completion date at registration
- June 2025
- Latest completion date
- January 2027
- Delay so far
- 15 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 21
- Sold or booked
- 72%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of NAAZ PLAZA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| NAAZ PLAZA | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- NAAZ PLAZA: covers 6 floors
Latest CC order on MahaRERA: dated 17/01/2023.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on NAAZ PLAZA every month.
NAAZ PLAZA: buildings, flats and land, as filed on MahaRERA
- Buildings: NAAZ PLAZA (6 floors, 25 units)
- Car parking: 1 covered, 9 open
- Land: 470 sq m (about 0.1 acres) · sanctioned built-up 821 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of NAAZ PLAZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
NAAZ PLAZA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about NAAZ PLAZA
What is the possession date of NAAZ PLAZA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NAAZ PLAZA in At Mamdapur, Raigarh is 30 January 2027 — 15 months later than 30 June 2025, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for NAAZ PLAZA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date NAAZ PLAZA's builder has filed on MahaRERA, the official one, is 30 January 2027, already 15 months later than the 30 June 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of NAAZ PLAZA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), NAAZ PLAZA's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "1) Poor booking response from customer. 2) Because of poor response our work was very slow. But now we have completed our 98 % Project"; to 30 September 2026, giving the reason "1) Poor booking response from customer. 2) Because of poor response our work was very slow.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of NAAZ PLAZA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NAAZ PLAZA in At Mamdapur, Raigarh is P52000046744.
Is NAAZ PLAZA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NAAZ PLAZA is registered as P52000046744 and its status is "Registered and active".
What is the construction status of NAAZ PLAZA?
According to GharKundli's check of MahaRERA records (updated October 2026), NAAZ PLAZA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NAAZ PLAZA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does NAAZ PLAZA have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is NAAZ PLAZA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), NAAZ PLAZA is registered on MahaRERA as P52000046744, its completion date has moved 15 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if NAAZ PLAZA's possession date changes?
The latest dates are on NAAZ PLAZA's MahaRERA page (P52000046744). GharKundli's Kundli Watch sends a free WhatsApp update on NAAZ PLAZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does NAAZ PLAZA have?
According to GharKundli's check of MahaRERA records (updated October 2026), NAAZ PLAZA has one building filed: NAAZ PLAZA with 6 floors and 25 units.
How much parking does NAAZ PLAZA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered and 9 open car parking spaces for NAAZ PLAZA.
How big is the land of NAAZ PLAZA?
According to GharKundli's check of MahaRERA records (updated October 2026), NAAZ PLAZA stands on 470 sq m of land (about 0.1 acres), with 821 sq m of sanctioned built-up area.
Where can I read reviews of NAAZ PLAZA?
Google Maps has reviews of NAAZ PLAZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is NAAZ PLAZA?
NAAZ PLAZA by PRESTIGE REALITY is in At Mamdapur, Raigarh (pincode 410101), Maharashtra, and is registered on MahaRERA as P52000046744, per GharKundli's check of MahaRERA records.
How many homes are in NAAZ PLAZA?
According to GharKundli's check of MahaRERA records (updated October 2026), NAAZ PLAZA has 21 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.
When was NAAZ PLAZA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), NAAZ PLAZA was registered on MahaRERA on 5 September 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on NAAZ PLAZA?
No court cases are listed for NAAZ PLAZA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of NAAZ PLAZA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRESTIGE REALITY, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of NAAZ PLAZA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in Karjat
- SWAMI AASHRAY
- 21 ENCLAVE
- Ratnamisha Villas
- Krishna Valley Phase I
- MUDRA AVENUE
- Hill Top Residency
- Gajvakra Heights
- MIRA RESIDENCY
Other projects by PRESTIGE REALITY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.