DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE
by DOSTI ENTERPRISES · Balkum, Thane West, ThaneAlso near Sandozbaugh
Possession date of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700054424, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
How the possession date of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE’s extension records on MahaRERA (P51700054424), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 3 court cases, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700054424
- Status
- Registered and active
- Builder
- DOSTI ENTERPRISES
- Location
- Balkum, Thane West, Thane · 400608
- Project type
- Residential / Group Housing
- Registered on
- 19 Jan 2024
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 384
- Sold or booked
- 35%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 14
Construction progress of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DOSTI MAPLE WING A - BUILDING NO 4 | 100% | 72% | 16% | 8% |
| DOSTI MAPLE WING B - BUILDING NO 3 | 100% | 100% | 45% | 5% |
Commencement certificate (CC), as filed on MahaRERA
- DOSTI MAPLE WING A - BUILDING NO 4: covers 33 floors
- DOSTI MAPLE WING B - BUILDING NO 3: covers 33 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE every month.
DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE: buildings, flats and land, as filed on MahaRERA
- Buildings: DOSTI MAPLE WING A - BUILDING NO 4 (35 floors, 192 units) · DOSTI MAPLE WING B - BUILDING NO 3 (35 floors, 196 units)
- Land: 1,662 sq m (about 0.4 acres) · sanctioned built-up 38,033 sq m · recreational space 14,199 sq m
The builder’s record and reviews
Dosti Enterprises (a group of 2 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 2 finished, all within the promised date; 14 still being built, none past the promised date yet. 21 complaints on MahaRERA across 9 projects.
Read Google reviews of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE
What is the possession date of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE in Balkum, Thane West, Thane is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE in Balkum, Thane West, Thane is P51700054424.
Is DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE is registered as P51700054424 and its status is "Registered and active".
What is the construction status of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 72% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE is registered on MahaRERA as P51700054424, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE's possession date changes?
The latest dates are on DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE's MahaRERA page (P51700054424). GharKundli's Kundli Watch sends a free WhatsApp update on DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE have?
According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE has 2 buildings filed: DOSTI MAPLE WING A - BUILDING NO 4 with 35 floors and 192 units; DOSTI MAPLE WING B - BUILDING NO 3 with 35 floors and 196 units.
How big is the land of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE stands on 1,662 sq m of land (about 0.4 acres), with 38,033 sq m of sanctioned built-up area and 14,199 sq m of recreational open space.
What is the track record of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Dosti Enterprises (a group of 2 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 2 finished, all within the promised date; 14 still being built, none past the promised date yet. 21 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
Google Maps has reviews of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE by DOSTI ENTERPRISES is in Balkum, Thane West, Thane (pincode 400608), near Sandozbaugh, Maharashtra, and is registered on MahaRERA as P51700054424, per GharKundli's check of MahaRERA records.
How many homes are in DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE has 384 homes in 2 towers registered on MahaRERA, and 35% of them are sold or booked.
When was DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE was registered on MahaRERA on 19 January 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
3 court cases are listed for DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is DOSTI ENTERPRISES, which has 14 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of DOSTI WESTCOUNTY - PHASE 6 - DOSTI MAPLE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in pincode 400608
- HIGHLAND SPRINGS B4- C WING
- HIGHLAND SPRINGS B4 D WING
- Vaikunth Cluster 3 Tower 2
- Mahavir Bliss
- SHRADDHA PENINSULA
- MARKANDEY SQUARE
- Mangeshi heights
- ONE DOSTI
Other projects by DOSTI ENTERPRISES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.