GEBI PRERNA
by Ashwin kumar Jain · Shelar, ThaneAlso near Dandekarwadi
Possession date of GEBI PRERNA: 30 April 2029, moved from 30 June 2021 (90 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700014458, and currently active. Its completion date has moved from June 2021 to April 2029: 90 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about GEBI PRERNA?
How the possession date of GEBI PRERNA has moved
30 June 2021
Completion date given when the project was registered
29 June 2022
Extended at the builder's request (MahaRERA application EXT51700010299)
Reason the builder gave MahaRERA:
“The project has got delayed due to non-payment of dues by customers and lack of further sales. Funds have dried up and we are awaiting funding lines from bank. We hope to restart our project in a month's time and complete by June 2022. we a…” Read the full reason
“The project has got delayed due to non-payment of dues by customers and lack of further sales. Funds have dried up and we are awaiting funding lines from bank. We hope to restart our project in a month's time and complete by June 2022. we are also applying to MMRDA for revalidation of our CC.”31 December 2025
Extended at the builder's request (MahaRERA application EXT51700015409)
Reason the builder gave MahaRERA:
“Due to the delay in getting approvals and delay due to COVID, we have come under tremendous financial stress. We have managed to complete two buildings in the last two years. Banks are not willing to fund as as we have very thin margin of p…” Read the full reason
“Due to the delay in getting approvals and delay due to COVID, we have come under tremendous financial stress. We have managed to complete two buildings in the last two years. Banks are not willing to fund as as we have very thin margin of profit. We are tying up with a contractor for the completion of the balance of seven buildings in the project on Barter basis. Being in the low-cost housing category we wish to complete the project anyhow as our customers are all middle and lower-class. We wish to give them the dream house we promised.”31 December 2028
Extended at the builder's request (MahaRERA application EA30122519138)
Reason the builder gave MahaRERA: “as given earlier”
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: GEBI PRERNA’s extension records on MahaRERA (P51700014458), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GEBI PRERNA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700014458
- Status
- Registered and active
- Builder
- Ashwin kumar Jain
- Location
- Shelar, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 4 Dec 2017
- Completion date at registration
- June 2021
- Latest completion date
- April 2029
- Delay so far
- 90 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 280
- Sold or booked
- 31%
- Towers
- 9
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of GEBI PRERNA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 1 | 100% | 25% | 50% | 0% |
| 3 | 100% | 25% | 25% | 0% |
| 2 | 100% | 25% | 50% | 0% |
| 5 | 100% | 25% | 50% | 0% |
| 7 | 100% | 100% | 100% | 50% |
| 8 | 100% | 100% | 100% | 50% |
| 6 | 0% | 0% | 0% | 0% |
| 4 | 0% | 0% | 0% | 0% |
| 9 | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- 1: covers 1 floors
- 3: covers 9 floors
- 2: covers 1 floors
- 5: covers 1 floors
- 7: covers 7 floors
- 8: covers 7 floors
- 6: covers 7 floors
- 4: covers 7 floors
- 9: covers 7 floors
Latest CC order on MahaRERA: dated 12/12/2017.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GEBI PRERNA every month.
GEBI PRERNA: buildings, flats and land, as filed on MahaRERA
- Buildings: 1 (8 floors, 28 units) · 3 (11 floors, 35 units) · 2 (8 floors, 28 units) · 5 (8 floors, 28 units) · 7 (8 floors, 28 units) · 8 (8 floors, 28 units) · 6 (11 floors, 35 units) · 4 (11 floors, 35 units) · and 1 more
- Car parking: 1 covered
- Land: 9,300 sq m (about 2.3 acres) · sanctioned built-up 8,715 sq m · recreational space 1,871 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of GEBI PRERNA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GEBI PRERNA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GEBI PRERNA
What is the possession date of GEBI PRERNA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for GEBI PRERNA in Shelar, Thane is 30 April 2029 — 90 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for GEBI PRERNA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GEBI PRERNA's builder has filed on MahaRERA, the official one, is 30 April 2029, already 90 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of GEBI PRERNA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), GEBI PRERNA's builder applied to MahaRERA to extend the completion date 3 times: to 29 June 2022, giving the reason "The project has got delayed due to non-payment of dues by customers and lack of further sales. Funds have dried up and we are awaiting funding lines from bank. We hope to restart our project in a month's time and complete by June 2022. we are also applying to MMRDA for revalidation of our CC."; to 31 December 2025, giving the reason "Due to the delay in getting approvals and delay due to COVID, we have come under tremendous financial stress. We have managed to complete two buildings in the last two years. Banks are not willing to fund as as we have very thin margin of profit. We are tying up with a contractor for the completion of the balance of seven buildings in the project on Barter basis. Being in the low-cost housing category we wish to complete the project anyhow as our customers are all middle and lower-class. We wish to give them the dream house we promised."; to 31 December 2028, giving the reason "as given earlier". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of GEBI PRERNA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of GEBI PRERNA in Shelar, Thane is P51700014458.
Is GEBI PRERNA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GEBI PRERNA is registered as P51700014458 and its status is "Registered and active".
What is the construction status of GEBI PRERNA?
According to GharKundli's check of MahaRERA records (updated October 2026), GEBI PRERNA's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 100% across 9 towers. GharKundli's full report compares construction progress with the deadline.
Does GEBI PRERNA have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is GEBI PRERNA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), GEBI PRERNA is registered on MahaRERA as P51700014458, its completion date has moved 90 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if GEBI PRERNA's possession date changes?
The latest dates are on GEBI PRERNA's MahaRERA page (P51700014458). GharKundli's Kundli Watch sends a free WhatsApp update on GEBI PRERNA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GEBI PRERNA have?
According to GharKundli's check of MahaRERA records (updated October 2026), GEBI PRERNA has 9 buildings filed: 1 with 8 floors and 28 units; 3 with 11 floors and 35 units; 2 with 8 floors and 28 units; 5 with 8 floors and 28 units; 7 with 8 floors and 28 units; 8 with 8 floors and 28 units; and 3 more.
How much parking does GEBI PRERNA have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for GEBI PRERNA.
How big is the land of GEBI PRERNA?
According to GharKundli's check of MahaRERA records (updated October 2026), GEBI PRERNA stands on 9,300 sq m of land (about 2.3 acres), with 8,715 sq m of sanctioned built-up area and 1,871 sq m of recreational open space.
Where can I read reviews of GEBI PRERNA?
Google Maps has reviews of GEBI PRERNA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GEBI PRERNA?
GEBI PRERNA by Ashwin kumar Jain is in Shelar, Thane (pincode 421302), near Dandekarwadi, Maharashtra, and is registered on MahaRERA as P51700014458, per GharKundli's check of MahaRERA records.
How many homes are in GEBI PRERNA?
According to GharKundli's check of MahaRERA records (updated October 2026), GEBI PRERNA has 280 homes in 9 towers registered on MahaRERA, and 31% of them are sold or booked.
When was GEBI PRERNA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), GEBI PRERNA was registered on MahaRERA on 4 December 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on GEBI PRERNA?
No court cases are listed for GEBI PRERNA on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of GEBI PRERNA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Ashwin kumar Jain.
Check it yourself on MahaRERA
- How to check the possession date of GEBI PRERNA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in pincode 421302
- ARIHANT CITY PHASE-II - K BUILDING
- ASHOKA COMPLEX
- REGAL SQUARE PH 4 TOWER 6 AND 8
- NEELKANTH SADAN
- Raghunath Heights
- ROYAL PARK
- SAI DEEP RESIDENCY
- KOHINOOR UPTOWN T1 & T6
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.