ANTALIYA
by PLATINUM REALTY AND INFRASTRUCTURE PRIVATE LIMITED · Dandekarwadi, ThaneAlso near Bhiwandi, Kamatghar, Naupada
Possession date of ANTALIYA: 30 April 2029, moved from 30 December 2024 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51700003659, and currently active. Its completion date has moved from December 2024 to April 2029: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about ANTALIYA?
How the possession date of ANTALIYA has moved
30 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51700025482)
Reason the builder gave MahaRERA:
“We received CC on – 06.07.2019 . We received Rera registration on 09.09.2021. Due to financial slowdown . we are unable to complete our project on time. Till date 80% construction of project has been completed. We assure that will complete…” Read the full reason
“We received CC on – 06.07.2019 . We received Rera registration on 09.09.2021. Due to financial slowdown . we are unable to complete our project on time. Till date 80% construction of project has been completed. We assure that will complete project with in one year extension time line(30-12-2025).”31 December 2028
Extended at the builder's request (MahaRERA application EA09122518586)
Reason the builder gave MahaRERA: “revise CC yet to come til now only 9 floor approved ,it is going to extent till 16 floor.”
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: ANTALIYA’s extension records on MahaRERA (P51700003659), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on ANTALIYA
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700003659
- Status
- Registered and active
- Builder
- PLATINUM REALTY AND INFRASTRUCTURE PRIVATE LIMITED
- Location
- Dandekarwadi, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 6 Aug 2017
- Completion date at registration
- December 2024
- Latest completion date
- April 2029
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 94
- Sold or booked
- 51%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of ANTALIYA, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| ANTALIYA | 100% | 100% | 30% | 5% |
Commencement certificate (CC), as filed on MahaRERA
- ANTALIYA: covers 9 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on ANTALIYA every month.
ANTALIYA: buildings, flats and land, as filed on MahaRERA
- Buildings: ANTALIYA (11 floors, 94 units)
- Land: 7,408 sq m (about 1.8 acres) · sanctioned built-up 6,266 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Moonshine Realtors (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 24 months late). 7 complaints on MahaRERA across 2 projects.
Read Google reviews of ANTALIYA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
ANTALIYA: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about ANTALIYA
What is the possession date of ANTALIYA?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for ANTALIYA in Dandekarwadi, Thane is 30 April 2029 — 48 months later than 30 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for ANTALIYA?
Builders and listing sites often quote an earlier "target" date for handover. The completion date ANTALIYA's builder has filed on MahaRERA, the official one, is 30 April 2029, already 48 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of ANTALIYA extended?
According to GharKundli's check of MahaRERA records (updated October 2026), ANTALIYA's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "We received CC on – 06.07.2019 . We received Rera registration on 09.09.2021. Due to financial slowdown . we are unable to complete our project on time. Till date 80% construction of project has been completed. We assure that will complete project with in one year extension time line(30-12-2025)."; to 31 December 2028, giving the reason "revise CC yet to come til now only 9 floor approved ,it is going to extent till 16 floor.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of ANTALIYA?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of ANTALIYA in Dandekarwadi, Thane is P51700003659.
Is ANTALIYA registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANTALIYA is registered as P51700003659 and its status is "Registered and active".
What is the construction status of ANTALIYA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANTALIYA's status on MahaRERA is "Registered and active". As filed by the builder, slab work on ANTALIYA is 100% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.
Does ANTALIYA have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is ANTALIYA safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), ANTALIYA is registered on MahaRERA as P51700003659, its completion date has moved 48 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if ANTALIYA's possession date changes?
The latest dates are on ANTALIYA's MahaRERA page (P51700003659). GharKundli's Kundli Watch sends a free WhatsApp update on ANTALIYA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does ANTALIYA have?
According to GharKundli's check of MahaRERA records (updated October 2026), ANTALIYA has one building filed: ANTALIYA with 11 floors and 94 units.
How big is the land of ANTALIYA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANTALIYA stands on 7,408 sq m of land (about 1.8 acres), with 6,266 sq m of sanctioned built-up area.
What is the track record of ANTALIYA's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Moonshine Realtors (a group of 2 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, 2 past the promised date (typically 24 months late). 7 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of ANTALIYA?
Google Maps has reviews of ANTALIYA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is ANTALIYA?
ANTALIYA by PLATINUM REALTY AND INFRASTRUCTURE PRIVATE LIMITED is in Dandekarwadi, Thane (pincode 421302), near Bhiwandi, Kamatghar, Naupada, Maharashtra, and is registered on MahaRERA as P51700003659, per GharKundli's check of MahaRERA records.
How many homes are in ANTALIYA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANTALIYA has 94 homes in 1 tower registered on MahaRERA, and 51% of them are sold or booked.
When was ANTALIYA registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), ANTALIYA was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on ANTALIYA?
No court cases are listed for ANTALIYA on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of ANTALIYA?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PLATINUM REALTY AND INFRASTRUCTURE PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of ANTALIYA
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Thane →
Other projects in pincode 421302
- ARIHANT CITY PHASE-II - K BUILDING
- ASHOKA COMPLEX
- REGAL SQUARE PH 4 TOWER 6 AND 8
- NEELKANTH SADAN
- Raghunath Heights
- ROYAL PARK
- SAI DEEP RESIDENCY
- KOHINOOR UPTOWN T1 & T6
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.